The Arrium IsaMill from Design through Commissioning and Optimisation

- Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 10
- File Size:
- 1525 KB
- Publication Date:
- Sep 7, 2015
Abstract
Arrium’s magnetite concentrator has recently completed a modification program to improve the process that has been in operation in Whyalla, South Australia for the previous seven years. The magnetite concentrate is pumped via pipeline to the coast and serves as pellet plant feed, eventually being turned into steel in the Whyalla blast furnace. With the addition of a new 3MW IsaMill at the concentrator, the plant has seen increased production from a reduced feed grade, enabling Arrium to treat ores previously stockpiled as waste. This paper will focus on the design work and commissioning of the fine grinding circuit along with the year of optimisation that followed, taking the IsaMill up to 350+ tph of throughput.CITATION:Larson, M, Anderson, G, Mativenga, M and Stanton, C, 2015. The Arrium IsaMill from design through commissioning and optimisation, in Proceedings MetPlant 2015, pp 110–119 (The Australasian Institute of Mining and Metallurgy: Melbourne).
Citation
APA:
(2015) The Arrium IsaMill from Design through Commissioning and OptimisationMLA: The Arrium IsaMill from Design through Commissioning and Optimisation. The Australasian Institute of Mining and Metallurgy, 2015.