The Atlanta West Area CSO Storage Tunnel and Pumping Station Project—15 Months of Design Accomplished Within 10 Months

Society for Mining, Metallurgy & Exploration
Lawrence A. Williamson George D. Barnes Refik Elibay
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
10
File Size:
2481 KB
Publication Date:
Jan 1, 2005

Abstract

Under an extremely aggressive schedule, final design of 13.5 km (8.4 miles) miles of 8.2 m (27 ft) diameter deep rock tunnel, 322 ML/day (85 million gallons / day)submersible pumping station and associated facilities were accomplished ahead of a federal court mandated consent decree schedule. Challenges overcome by the project team in enabling timely completion of the construction documents will be presented. Discussion includes evolution of final design, consideration of future O&M requirements, and risks identified for construction and operations, together with measures to manage and proactively prepare for such risks.
Citation

APA: Lawrence A. Williamson George D. Barnes Refik Elibay  (2005)  The Atlanta West Area CSO Storage Tunnel and Pumping Station Project—15 Months of Design Accomplished Within 10 Months

MLA: Lawrence A. Williamson George D. Barnes Refik Elibay The Atlanta West Area CSO Storage Tunnel and Pumping Station Project—15 Months of Design Accomplished Within 10 Months. Society for Mining, Metallurgy & Exploration, 2005.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account