The Cerro Verde 2 Concentrator: Design, Start Up and Operation

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 12
- File Size:
- 744 KB
- Publication Date:
- Jan 1, 2017
Abstract
"The Cerro Verde copper-molybdenum mining complex is located near Arequipa, Peru. A 108,000 t/d copper concentrator (C1 concentrator) commenced operation in late 2006 and was debottlenecked to a 120,000 t/d capacity in 2011. A feasibility study, initiated in May 2010, assessed the potential for expanding the processing rate of the large Cerro Verde sulfide reserve via the installation of a second, stand-alone, concentrator (C2 concentrator) capable of processing a nominal 240,000 t/d ore. The feasibility study was successful and the project advanced through engineering, permitting and construction. Ramp up to nameplate capacity was ahead of schedule. The overall project was completed on schedule and within budget. The details of the project and supporting components are described. The design philosophy and design basis of the concentrator facilities are discussed as are factors that influenced the concentrator layout. Risk mitigation features included in the design are reviewed. The factors that drove the successful and rapid ramp up to nameplate capacity are discussed. Operational experiences in the first year of plant operation and project lessons learned are described. INTRODUCTION/BACKGROUND Sociedad Minera Cerro Verde S.A.A. (SMCV) operates a copper mine near Arequipa in southern Peru. Small scale operations operated intermittently until 1970 when the deposit reverted to the ownership of Minero Perú S.A (Peruvian government). Minero Perú S.A. commenced mining and processing of oxide reserves in 1972 and placed an SX-EW plant into production in 1976. The ownership of the property has changed hands several times over the years. Minero Perú sold Cerro Verde to Cyprus Climax Metals in 1994. Cyprus was acquired by Phelps Dodge in 1999. Freeport-McMoRan (FCX) acquired Phelps Dodge in 2007. Several studies were undertaken during the 1990’s that tried to establish the economic justification to process the large primary sulfide resource that underlies the surface oxide deposit. None of these studies produced an economic conclusion until a feasibility study was completed by Phelps Dodge and SMCV in 2004. This study provided the economic justification for the construction of a 108,000 t/d concentrator during 2005 and 2006. The key to the success of this study was identifying a water source that was sufficient to support processing economies of scale. Concentrator operations commenced in late 2006. The original design production rate of 108,000 t/d was achieved on a 30 day moving average basis on the 266th day after ore was first introduced. During 2009, studies and evaluations were performed that had the objective of addressing observed concentrator bottlenecks to allow a production rate of 120,000 t/d to be achieved. The 120,000 t/d figure represents the sustainable production limits associated with the installed primary crusher and tailing thickeners which would have been prohibitively expensive to upgrade. Debottlenecking activities were implemented during 2010 allowing sustained production rates of 120,000 t/d to be achieved."
Citation
APA:
(2017) The Cerro Verde 2 Concentrator: Design, Start Up and OperationMLA: The Cerro Verde 2 Concentrator: Design, Start Up and Operation. Society for Mining, Metallurgy & Exploration, 2017.