The Function Of Shotcrete In Support And Lining Of The Vancouver Railway Tunnel

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 12
- File Size:
- 655 KB
- Publication Date:
- Jan 1, 1970
Abstract
The Canadian National Railway system is completing construction of the first major tunnel in North America to use the coarse-aggregate (+ ½ -in.) shotcrete technique of primary support and lining. The tunnel was driven 29 X 20 ft in cross section, 10,760 ft long, passing under an industrial and residential area of Vancouver. With the exception of 1400 ft in soil (mainly impervious tills), the tunnel passes through a very young series of flat-lying sedimentary beds, to a large extent so incompletely consolidated as to fall apart on exposure. For a conventional steel-support system, it was estimated 8 WF, 28-lb steel should be used at 5-ft centers. Cost of erection including lagging would amount to $120 per linear ft of tunnel at 304 per lb. With 8-in. concrete cover on the steel, lining would cost $280 per linear ft at $82 per cu yd. Thus, minimum cost of support and lining would have amounted to $400 per linear ft. It is now estimated that at least 90% of the rock tunnel would have required support and 100 % required lining. Specified shotcrete support was 6 in. in the arch and 4 in. in the walls. Cost of this work was roughly $100 per linear ft. In addition, another $10-$12 per ft has been incurred in drainage and waterproofing wet areas and in measures to correct experimental and operational errors, thus finalizing the support as a lining (Fig. 1). The tunnel was driven three shifts five days weekly, no blasting being allowed by city ordinance between midnight and 7.00 a.m. A six-drill jumbo was used to drill a 10-ft round, 110 holes blasted three times daily. A 2-in. layer of shotcrete was applied to the newly blasted arch commencing within 45 min of blasting. This was done from a flying deck that extended over the muck pile from the jumbo (Fig. 2). Also during the mucking cycle, the preceding incomplete arch support was brought up to 6-in. specification. The walls were sprayed 4 in. thick during the drilling cycle (Fig. 3). The shotcrete machines and aggregate bins were mounted on the jumbo.
Citation
APA:
(1970) The Function Of Shotcrete In Support And Lining Of The Vancouver Railway TunnelMLA: The Function Of Shotcrete In Support And Lining Of The Vancouver Railway Tunnel. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1970.