The Little Lake Harris Bridge Settlement Restoration Project: Lessons Learned

Deep Foundations Institute
Amr Sallam Moataz Hassan David Thompson
Organization:
Deep Foundations Institute
Pages:
9
File Size:
3677 KB
Publication Date:
Jan 1, 2015

Abstract

"The Little Lake Harris (LLH) Bridge was constructed in 1951 to replace the eastwest County Road 48 Bridge connecting the towns of Howey-in-the-Hills and Astatula in Lake County, Florida, United States. The 78-span bridge carries two lanes of traffic, is 3,130 feet long, and 36.1 feet wide. The concrete deck is supported by steel I-girders carried by one row of 18-inch square precast concrete driven pile. In the late 1980's, slight settlements were observed in several bents. In 1990, Florida Department of Transportation (FDOT) initiated annual survey of deck elevations during bridge inspections to monitor settlement. Due to the slow nature and magnitude of settlement, substructure instability was not a major concern to the department. However, public concern over the settlement and rough ride of the bridge continued to rise. FDOT contracted Kisinger Campo & Associates Corp. (KCA) to provide the needed design to correct the dips in the riding surface and minimize future settlement. KCA's initial design was based on the concept of ""helper bents"" at the settled bents in order to restore the bridge to original elevation. Estimated construction cost for seven helper bents was about $3.3M. FDOT requested evaluating other alternatives to reduce the cost of the bridge restoration. KCA involved the geotechnical consultant, Terracon Consultants, Inc. (Terracon), to perform a peer review and provide an economical alternative solution. Jacking and shimming the bridge was determined to be both technically viable and economical with a total cost of less than $300K. The design was completed in March 2010 and construction was completed in February 2011. This paper provides an overview of the LLH Bridge history, summarizes the evolution of the design methodology including the findings of the geotechnical study and presents lessons learned during the design and construction of the project.INTRODUCTIONThe Safety and Preservation of the State Highway System is the top priority of the FDOT. Therefore, FDOT initiated a bridge management program that starts with conducting biennial safety inspections performed by Certified Bridge Inspectors (CBI). The inspection reports together with the CBI’s recommendations are reviewed by a registered Professional Engineer (PE) and work orders are issued with priority ranking depending on the severity of the bridge deficiencies. If the scope of work is considered beyond the in-house crews’ capability, the work is then included in a contract for and bid. LLH Bridge was a little different. It was initiated in direct response to number of complaints the FDOT District 5 Structures Maintenance Office (D5SMO) received regarding settlement of the Little Lake Harris Bridge."
Citation

APA: Amr Sallam Moataz Hassan David Thompson  (2015)  The Little Lake Harris Bridge Settlement Restoration Project: Lessons Learned

MLA: Amr Sallam Moataz Hassan David Thompson The Little Lake Harris Bridge Settlement Restoration Project: Lessons Learned. Deep Foundations Institute, 2015.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account