The Noranda Smelter

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 45
- File Size:
- 11653 KB
- Publication Date:
- Jan 1, 1930
Abstract
The Noranda smelter was built by Noranda Mines, Limited, from the designs of A. E. Wheeler, consulting metallurgist, New York, for the reduction of ores and concentrates from the Horne mine, and to treat, on a custom basis, ores and concentrates from other mines in the Rouyn district. The smelter is situated at Noranda in western Quebec, about 330 miles directly north of Toronto. Ground was first broken for construction in November, 1925, before the completion of the branch railway into the district, which was not finished until October, 1926. After many difficulties and delays due to the Jack 'of transportation and the severe weather during the winter months, the smelter was started in December, 1927, and the first blister copper was poured on December 17th. The smelter was built throughout in two duplicate units, each with a rated capacity of 500 tons of ore per day. Operations were started with only one unit, and after several months it was found that one unit alone would smelt 1,000 tons of ore per day. At this time only one shaft, No. 3, existed, and its hoisting capacity and the capacity of the original crushing plant were insufficient to supply ore for two units at the increased tonnage. Accordingly No. 4 shaft was sunk and a new crushing plant provided to handle the ore hoisted there. This work was completed in the latter part of November, 1929, and since that time both smelter units have been operating.
Citation
APA:
(1930) The Noranda SmelterMLA: The Noranda Smelter. Canadian Institute of Mining, Metallurgy and Petroleum, 1930.