The Start-up and Operation of the Gibraltar Mines SX-EW Plant (e864bb9e-42ee-4b0f-8109-3374578f0d92)

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 11
- File Size:
- 357 KB
- Publication Date:
- Jan 1, 1988
Abstract
"Gibraltar Mines Ltd. has been operating its open pit copper mine for fifteen years. In that time over 140 million tons of waste and low grade material has been placed on the mine waste dumps. Laboratory and in-situ testing indicated that enough leachable copper was recoverable from the dumps to justify a leaching operation which would include the construction of a solvent extraction-electrowinning plant. The plant, which was commissioned in October, 1984 was designed to process 3,000 usgpm of dilute copper solution to produce 5,000 tons per year of high quality cathode copper.This paper deals with the start up and initial year of operation of Gibraltar's SX-EW plant. The three areas: leaching solvent extraction and electrowinning are presented with emphasis on the innovations which were made to help overcome the problems unique to die Gibraltar operation.THE LEACHING CIRCUITThe mines waste dumps are leached to produce a pregnant copper solution as feed to the SX-EW plant. To achieve this the dumps are sprinkled with a mildly acidic solution which percolates through the dump. In travelling through the dumps the solution contacts the surfaces of the liberated copper minerals and disolves the soluble copper into the form of copper sulphate. The leaching reaction is achieved by a combination of bacterial action to oxidize the suphides and solublization of the copper into the acid solution.For the bacterial action to occur the dumps must be at or near the ideal pH of 1.9 - 2.1 and the necessary elements of the reaction must be present. Because a bacterial reaction is involved there is a lag time between the time when the conditions for bacterial growth are achieved and when the bacteria are in their active growth phase. Laboratory tests with Gibraltar ore indicated that bacterial action takes two to three months to reach its maximum rate. See figure 1.The expected lag time for the planned rate of bacterial leaching prompted Gibraltar to start irrigating the dumps in late June 1986 for a plant start up in early fall. The lag time proved to be longer than expected and the dumps took until November to start producing copper at the expected rate. See figure 2."
Citation
APA:
(1988) The Start-up and Operation of the Gibraltar Mines SX-EW Plant (e864bb9e-42ee-4b0f-8109-3374578f0d92)MLA: The Start-up and Operation of the Gibraltar Mines SX-EW Plant (e864bb9e-42ee-4b0f-8109-3374578f0d92). Canadian Institute of Mining, Metallurgy and Petroleum, 1988.