The True Cost of Boulders in a Soft Ground Tunnel

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 5
- File Size:
- 309 KB
- Publication Date:
- Jan 1, 2003
Abstract
The Columbia Slough Consolidation Conduit Project is a 12 ft. 0 in. inside diameter—15 ft. 4 in. excavated diameter tunnel, 8,300 lf. in length. The tunnel is divided in two parts a 4,460 lf. reach to the West and a 3,770 lf. reach to the East separated by a flow regulation structure in the middle. The project was built for the City of Portland, Oregon Bureau of Environmental Services (BES) by the Frank Coluccio Construction Company (FCCC) Seattle, Washington under a $22,600,000.00 contract starting in 1998 and completing the contract in 2000 at a total cost to the City of $25,448,000. An increase of 12.6% from the original contract. The tunnel was constructed in an alluvial sediment that ranges up to 1,500 feet thick. The sediment varies from ?ne silty sand and sandy silt (SM-ML) to coarse sand and gravel (GP-GM) with varying quantities of cobbles and boulders. Most of the tunnel was constructed above the water table although one reach of almost 1,000 lf. had water to above the tunnel crown. The contractor, FCCC, used a Lovat 15 ft. 3 in.900 hp shielded TBM with multiple doors (4) of variable opening to excavate and support the tunnel. Tunnel supports were 5 in. WF 16 lbs. per foot at 4 ft. spacing and4 in. Douglas Fir lagging. Tunnel excavation was worked in 10 hour shifts with additional equipment maintenance and repair on the off time. The original Geotechnical Design Summary Report (GDSR) established a baseline for contractual purposes of slightly over 5 boulders (between 12 in. and48 in.) per foot of tunnel. (Table 1) At the pre-bid conference, three test pits were excavated to approximately tunnel invert, one at each end of the project and one in the middle near the flow regulation structure. The test pits encountered a few boulders but did not seem to support the five boulders per foot (varied from one boulder per foot of tunnel to eight b/lf.). Subsequent to the pre-bid meeting and the test pits, BES issued any addenda which changed the baseline boulder quantity in the GDSR to 1.7 boulders per foot of tunnel (varied from0.2 to 3.5 boulders per foot) a reduction of 67% from the original baseline. It is interesting to note the two separate tunnel reaches and how they were evaluated in the GDSR. Originally the Eastern portion of the work was projected at5.08 boulders per foot of tunnel and the Western portion at 5.30 boulders per foot of tunnel for a variance of less than 5%. In the revised quantity the Eastern portion was projected at 2.01 boulders per foot of tunnel and the Western portion at 1.42 boulders
Citation
APA:
(2003) The True Cost of Boulders in a Soft Ground TunnelMLA: The True Cost of Boulders in a Soft Ground Tunnel. Society for Mining, Metallurgy & Exploration, 2003.