Tunnel Boring Machine Concept for Converging Ground

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 15
- File Size:
- 595 KB
- Publication Date:
- Jan 1, 1995
Abstract
The Yacambu Irrigation Tunnel Project of 34 km, 5 meter diameter circular and horseshoe section, has been under construction since the early 1970's. Notable among the excavation challenges is high ground cover of 3,000m creating large lithostatic pressures in the tunnel alignment with subsequent plastic flow of the ground in the tunnel walls. The tunnel may converge from small amounts to 1 or more meters of diameter over long sections. Several excavation techniques have been attempted but all without desired results. The paper proposes a new machine concept that uses the history of ground experience as its basis for design.
Citation
APA:
(1995) Tunnel Boring Machine Concept for Converging GroundMLA: Tunnel Boring Machine Concept for Converging Ground. Society for Mining, Metallurgy & Exploration, 1995.