? A BARGE WILL BE INSTALLED IN THE BOTTOM OF A  COMPLETED PIT.  ? THE PROVEN BAUER CUTTER TECHNOLOGY WILL BE  INSTALLED ON THE BARGE AND A DEWATERING PLANT  WILL BE INSTALLED NEAR THE BASE OF THE PIT RAMP.  ? THE WATER LEVEL IN THE PIT WILL BE RAISED BY  20- 40 METRES AND REMAIN CONSTANT OVER DURATION  OF MINING.  ? THE CUTTER WILL BE LOWERED TO MINE 10 METRE  DEEP BENCHES ON A CHECKERBOARD PATTERN TO AN  ULTIMATE DEPTH OF 200 METRES.  ? THE 5? MINUS CUTTINGS WILL BE PUMPED TO THE  DEWATERING PLANT, DEWATERED, AND TRUCKED TO  SURFACE.