Research on the Stability Analysis of TDM Column Composite Foundation Supported EmbankmentBy Song-yu Liu, Chao Yan, Yong-feng Deng
"In order to investigate the stability of embankment on soft subgrade improved by T-shaped deep mixed column composite foundation, the internal forces and failure modes of columns were analyzed on the
Jan 1, 2015
-
Case Study: Feather River West Levee Program Cutoff WallsBy Kyle R. Lackner, Jared P. Williams
"The Sutter Butte Flood Control Agency initiated the Feather River West Levee (FRWL) Program in 2010 to bring 35 miles of levee along the Feather River into compliance with applicable Federal and Stat
Jan 1, 2016
-
Two Miles of Anchored Bulkhead Supports Howard Frankland Bridge MegaprojectBy Casey D. Shanahan, Dustin Walkenhorst
The Howard Frankland Bridge megaproject consists of a new, 3.2-mile (5.1 km) bridge extending I-275 across Tampa Bay. Two steel sheet pile and combi-wall bulkheads with a total wall length of over 11,
Oct 31, 2023
-
Reliability Analysis Of Load Bearing Capacity Of Single Pile Placed Adjacent To Existing Buried Conduit Or Utility TunnelBy Amit Srivastava, Monica Malhotra
In a congested city or urban area, so called “lifeline of the city”, i.e. Gas, Electricity, telecommunication, as well as other utilities or facilities are supplied or transported underground through
Sep 1, 2022
-
Strength and Deformations of Piles Supporting Transient Pipe Anchors in Heavy Industrial PipelinesBy Konstantin G. Ashkinadze
The paper considers performance of piles supporting transient pipe anchors in heavy industrial pipelines. Events such as pump trips or opening and closing of large valves produce short-term dynamic pu
Jan 1, 2016
-
-
Philadelphia Dock Story—Pile Challenges at Delaware River (06bf9951-abf5-4656-aab7-81fa955662d4)By Craig H. Olson
"Anew ship dock at a Philadelphia area refinery will be capable of docking the largest tanker to travel the Delaware River, the Stena V-MAX, which will induce significant lateral loads. The loads at t
Jan 1, 2008
-
Philadelphia Dock Story—Pile Challenges at Delaware RiverBy Craig H. Olson
"A new ship dock at a Philadelphia area refinery will be capable of docking the largest tanker to travel the Delaware River, the Stena V-MAX, which will induce significant lateral loads. The loads at
Jan 1, 2008
-
Innovative Drilled Shaft Installation Process Through Existing Bridge FoundationsBy Tracy Brettmann
The Highway 146 Bridge Expansion Project across the Clear Creek Channel in Houston, Texas was designed on driven precast concrete piles. However, during construction, the piles along one side of the b
May 1, 2022
-
Wick Drain Guide Specification (Method)"1.0 DESCRIPTIONThis work consists of furnishing all necessary labor, equipment, and materials to install prefabricated vertical (wick) drains in the ground in accordance with the Plans and as specifi
Jan 1, 2014
-
Material Properties for Analysis of Deep Mixing Support SystemsBy Alex Grenoble, Alex Reeb, George Filz, Farzad Abedzadeh
"This paper summarizes available information on the characteristics and properties of deep-mixed soilcement produced by the wet method. The topics covered in this paper include: unit weight, unconfine
Jan 1, 2015
-
Design and Construction of Mixed Ground Working Platform for a CCR Surface ImpoundmentBy Juan M. Pestana, Jeremy M. Gasser, Cuneyt Gokmen, Paul J. Sabatini, William Tanner, Daniel J. Woeste
An access pathway and working platform were designed and constructed for equipment access for a Deep Soil Mixing (DSM) pilot study over a coal combustion residual (CCR) surface impoundment (SI). The D
Jan 1, 2019
-
A novel approach to bracing a piled retaining wall using temporary piled buttressesBy Will Frampton, Rachel Salter, Zoe Baldwin, Tim Hampshire
Cementation Skanska were responsible for the design and installation of 200 linear meters of contiguous bored piled retaining wall and approximately 1300 bearing piles for a new commercial arena devel
Oct 31, 2023
-
Digital Automation Of Geotechnical Sites – The Development And Essential Role Of An Industry Standardised Design FormatBy Scott White, Pishun Tantivangphaisal, Andrew Bell, Chris Barker
There has been considerable advancement in recent years in the tools, both software and hardware, available to allow efficient digitalization of site records during the construction of geotechnical wo
May 1, 2022
-
Piled-Raft Foundations in BelarusBy V. A. Sernov
"One of the ways to increase the bearing capacity of a piled foundation is to take into account soil resistance in the base of the raft. Piled raft is similar to shallow foundation and can transfer si
Jan 1, 2016
-
Pile Inspector's Guide To Hammers ? IntroductionThe pile inspector is a critical element in the quality control process necessary for a successful pile installation project. This guide is intended to provide the inspector with a basic understanding
Jan 1, 1995
-
Evaluation Of Pile Foundation Design Methods Using Load TestsBy SungWon Park
The efficiency of the current design methods for computing pile resistances is evaluated using field load-settlement tests results. Twelve load-settlement test data for drilled shafts and bored piles
Jan 1, 2009
-
Augered Cast-In-Place Pile Load Tests On The Cincinnati, Ohio/Northern Kentucky RiverfrontBy Theodore W. Vogelpohl
Augered cast-in-place piles have proven to be effective, adaptable and economical for projects throughout the Ohio River Valley. Specifically, they have been used extensively for high-rise structures,
Jan 1, 2005
-
Geo-Foundations Project Information Management Systems on a BudgetBy Jamey B. Rosen
As Project Information Management Systems (PIMS) technologies develop, the range of projects to which one can apply these technologies grows while the cost to apply them shrinks. In recent years, tech
Jan 1, 2019
-