    Strategic Underground Mine Access Design to Maximise the Net Present Value

    By P A. Grossman, J H. Rubinstein, M Brazil, K G. Sirinanda

    To date, the scheduling and access design of an underground mine have only been considered as two separate optimisation problems. First, access to the mine is designed and then the scheduling is compl

    Nov 24, 2014

  • AUSIMM
    Using Dynamic Simulation Throughout a Process Plant's Life Cycle

    Using Dynamic Simulation Throughout a Process Plant's Life Cycle

    Sep 13, 2010

  • AUSIMM
    A Platform for Managing and Analysing Atmospheric Data in Underground Coalmines

    By S J. Schafrik, Z Agioutantis, E C. Jong, K Luxbacher

    Real-time monitoring of mine operating parameters is available at most mines. However, access to these data for an individual operation is typically underutilised by mine managers and technical person

    Nov 4, 2015

  • AUSIMM
    Improving Blasting by a Team Approach at the Henty Gold Mine

    By R Wedmaier

    Henty Gold Mine is an underground operation producing 100 000 ounces of gold per annum. The original mining method used was flatbacking with paste fill. However, a non-entry method û uphole benching û

    Jan 1, 2001

  • AUSIMM
    Evolution and technical considerations to manage tailings at the RPP- 140 mining title (Antioquia - Colombia)

    By García B., Wolff E.

    In Colombia, northeast of Antioquia, there is a gold deposit that has produced continuously since the middle of the XIX century, located within mining title RPP-140, property of Gran Colombia Gold Seg

    Jun 17, 2024

  • AUSIMM
    Project Hobson – New Technology in Auckland

    By T Ireland

    The Project Hobson tunnel excavation was the first use in New Zealand of an earth pressure balance (EPB) tunnel boring machine (TBM). The tunnelling on the project was very successful and break-throug

    Mar 8, 2011

  • AUSIMM
    Recovery of Colloidal Gold from Oxidised Concentrate Wash Liquor - Further Improvement

    By R Symes

    The Fosterville Goldmine in Victoria Australia employs the BIOX« Process to liberate gold from its sulfidic flotation concentrate through bacterial oxidation. Gold occurrence is primarily as submicron

    Oct 29, 2012

  • AUSIMM
    Case Study - Total Life Cycle Planning for a Greenfield Site

    Central to any business is its Asset Management Plan which encapsulates the business context and key organisational objectives such as profitability, safety and environmental standards. Life Cycle Pl

    Jan 1, 2007

  • AUSIMM
    Metallurgical QA/QC – who needs it? The Olympic Dam experience

    By K Ehrig, V Liebezeit, E Macmillan

    The results from metallurgical test programs are used in feasibility studies for design of new plants and brownfield expansions, in long term mine plans, and to make decisions in an operating plant. T

    Sep 11, 2017

  • AUSIMM
    The evolution of structural and lithological domaining on the Spotted Quoll nickel sulfide mineral resource estimate

    By A D. Wulfse, C M. D Barton

    Underground fractured aquifers in the Ernest Henry deposit are to a large extent controlled by deposit scale brittle structures. The underground mine has been subdivided into nine water zones based on

    Mar 22, 2022

  • AUSIMM
    Special Purpose Simulator for Improved Estimation of Day-to-Day CIL/CIP Recoveries

    Sampling of CIL/CIP circuits is typically done by compositing samples of feed and tails over eight or 12 hour periods. As the residence time in the leaching tankage may be approximately 20 hours, the

    Jan 1, 2006

  • AUSIMM
    Matching Brown Coal to the Next Generation of Latrobe Valley Projects

    By G Love, S Maher

    In Victoria’s onshore Gippsland Basin, geology is driving brown coal developments, and geologists are key decision-makers. Prompted by volatile energy prices and the likelihood of a carbon constrained

    Aug 18, 2014

  • AUSIMM
    Bulk Low-Grade Mining at Mount Charlotte Mine

    By M F. Lee

    Although the Mt Charlotte gold resource was discovered in 1893, it was only in 1954 that geologists correctly interpreted drill data and defined a large low-grade orebody. The mine has been a large, l

    Jan 1, 2000

  • AUSIMM
    Slag volume effects on direct-reduced iron (DRI)-based electric furnace steelmaking

    By Q Zhuo, P C. Pistorius, M N. Al-Harbi

    A likely increasingly important pathway for future low-carbon ironmaking and steelmaking is the combination of gas-based direct reduction with electric furnace steelmaking (DRI-EAF route), or with ele

    Aug 21, 2024

  • AUSIMM
    Active explosion barrier conformance to the Australian Recognised Standard 21 – a total mine solution

    By A Späth

    Active explosion barriers are used to contain and suppress a methane gas and/or coal dust explosion propagation, including localised mine fires. Early research indicated that these active explosion ba

    Oct 12, 2022

  • AUSIMM
    Concentrator design – standard engineering practice versus geometallurgy and simulation

    By G Harbort, K Quan

    Traditional engineering practice for concentrator design uses a mixture of risk minimisation options and capital minimisation approaches. Often this is based on the preferences and experiences of the

    Sep 11, 2017

  • AUSIMM
    Modern X-Ray Diffraction Techniques as a Fast Industrial Analysis Method for Iron Ores - From Exploration to Process Control

    By L Gobbo

    X-ray diffraction (XRD) provides useful information about the composition of an ore sample in terms of quantification of crystalline phases and amorphous content. The use of new, fast detection system

    Jan 1, 2009

  • AUSIMM
    Advanced Customisable Leach Columns – A New Kinetic Testing Method to Simulate Site-specific Conditions

    By J Pearce, M Barteaux, S Pearce

    The prediction of how waste materials will evolve geochemically within waste storage facilities has been the subject of hundreds of thousands of hours researched by geoscientists globally. Despite the

    Jul 27, 2015

  • AUSIMM
    The Casposo Gold-Silver Project – Process Selection and Design

    By D Connelly

    Silver and gold bearing ore from the Troy Resources NL Casposo Gold-Silver Project, located within the San Juan Province of Argentina contains a complex mix of gold, silver, electrum and silver sulphi

    Aug 8, 2011

  • AUSIMM
    A comparison of the performance of fully versus partially encapsulated cable bolts based on laboratory-scale testing

    By P Hagan, S Wang, D Li, B Loh

    A study was undertaken to quantify the differences in performance between a full-length encapsulated cable bolt and a partially encapsulated cable bolt. Much research has been reported on the differen

    Nov 30, 2018