    Assessment and Mitigation of Ground Vibrations and Flyrock at a Limestone Quarry

    By R M. Bhatawdekar, A I. Theresraj, H S. Venkatesh

    Wadi Limestone Quarry is one of the largest captive mines of Associated Cement Companies Ltd, India. The mine management wanted to extend the excavation as close to the plant as possible for maximum e

    Jan 1, 1999

  • ISEE
    Rock Drilling on a Vertical Wall: Problem solving at Crazy Horse Memorial

    By Jeff Hermanson

    Every construction project has site specific problems that need to be dealt with. These problems may be created by the geology, location, weather, time constraints, etc. Once these problems have been

    Jan 1, 1996

  • ISEE
    Reducing Underwater Blast Damage with Air-Screens

    By Gregory L. Hempen

    "Pressure waves from submerged blasting can have adverse impacts on nearby structuresand on aquatic fauna. Underwater blasting is not allowed for some situations withoutmitigation of these adverse pre

    Jan 1, 1993

  • ISEE
    Blasting at the Valdez Creek Placer Mine, a Cost Savings Design for Sub Arctic Conditions

    By William E. Hill

    The blasting program at the Valdez Creek Placer Mine must deal with challenging situations throughout the year. During the short summer, extreme water conditions must be confronted, while the winter m

    Jan 1, 1994

  • ISEE
    Drilling and Cost Analysis Usign a Personal Computer and Spreadsheet

    By William D. Hissem

    The purpose of this paper is to advise people about the methods, use, and possible applications of current "personal computer" hardware and software with regard to the economic cost analysis of percus

    Jan 1, 1986

  • ISEE
    Blasting Procedures, Veterans Administration Medical Center, Birmingham, Alabama

    By Beau Bryson, Tony Cooley

    The following paper is a technical discussion depicting the type of blasting procedures used to control vibration levels. The blast vibration control criteria that was established and the type of moni

    Jan 1, 1985

  • ISEE
    Experiences and Applications with Wassara Water Hydraulic Down Hole Drilling Systems

    By Graeme Exelby

    The 4" Wassara water hammer was originally developed by G-Drill AB together with Swedish Mining Company LKAB for their underground long hole production drilling. Sandvik Rock Tools AB is responsible f

    Jan 1, 1998

  • ISEE
    What a Gas: Blasting Under Pressure (8726b99d-0c1c-4f90-bc37-7481da7b7d20)

    By Jerry R. Wallace

    This project consisted of blasting for expansion of a major interstate natural gas transmission pipeline pump station. The pump station handled 400-500 million cubic feet (11-14 million cubic meters)

    Jan 1, 1996

  • ISEE
    Changing Borehole Length to Improve Breakage: a Case History

    By Norman S. Smith, Richard L. Ash

    Many factors affect rock fragmentation from blasting. One variable seldom considered when designing blasts, however, is the borehole length. An example is described of how the length was adjusted to g

    Jan 1, 1976

  • ISEE
    Computer Aided Blast Design for Tunnels

    By J L. Jethwa, A G. Gaithankar

    The paper deals with a software method developed to design the optimum blast parameters for tunnels and mine roadways for a given set of geo-mining condition without any major discontinuity. The appli

    Jan 1, 1993

  • ISEE
    A Decade of Blasting at Martin Marietta Cement

    By J T. Keim

    Members and guests of the Society of Explosive Engineers, it's indeed a pleasure for a longtime practical user such as myself to have the ears of so many explosive experts for a few minutes just to ex

    Jan 1, 1978

  • ISEE
    Explosive Optimization Through the Use of a Cascade Loading Technique at Inco Limited - Manitoba Division

    By Christoper J. Hunter, Tony Mansel, Carl Kolada

    With a current trend toward Bulk Mining methods utilizing both large diameter uphole and downhole drilling, corresponding loading equipment and technology is required to safely and efficiently load th

    Jan 1, 1990

  • ISEE
    Calculation of the Model Structure of Emulsion Explosive

    By Wang Xuguang Shen Yingfeng

    Structure is the main aspect affecting the performance of emulsion explosive. Calculation of such structure parameters as osmosis pressure, interface area per unit volume etc. must be helpful to the u

    Jan 1, 1998

  • ISEE
    Dynamic Photoelastic Experiment on the Fracture Caused by a Blasting

    By Yuji: Wada Ogata, Kunihisa Katsuyama

    It is well known that a compressed stress wave reflects at the free face, it propagates to the backward as a tensile stress wave, and cracks grow when the tensile stress becomes the dynamic tensile st

    Jan 1, 1993

  • ISEE
    Damage Levels for Reinforced Concrete Columns Subject to Internal Explosive Charges

    By I. Petropouleas, J. Croll, R. Bassett

    A programme of tests on controlled internal explosions to a class of circular reinforced concrete columns, has allowed the relationships between the blast energy and the extent of local damage to be u

    Jan 1, 2006

  • ISEE
    Cosmar and Blasting

    By Lee W. Saperstien

    Section 709 of Public Law 95-87, "Surface Mining Control and Reclamation Act of 1977," requests the National Academy of Sciences to determine if the standards of the act are applicable to minerals oth

    Jan 1, 1979

  • ISEE
    Geologic Data for Blasting at the Minntac Mine

    By John Eloranta

    This paper is a case study showing the assembly of available rock property parameters for the purpose of blast design. Blast optimization now includes subsequent milling and requires a full knowledge

    Jan 1, 1996

  • ISEE
    The US DoD RBESCT Development of SAFER

    By William Yutmeyer, Meredith Hardwick

    Since 1996 there have been at least two teams formed within the U.S. Government to develop a consistent set of risk-based standards to be used to govern safety. The first of these was the Risk and Let

    Jan 1, 2007

  • ISEE
    Vibration and Ground Rupture Criteria for Buried Pipelines

    By Lewis L. Oriard

    This paper describes the process of developing blasting specifications for 850 miles of new pipe trench running parallel to an existing high-pressure gas pipeline, often with as little as 14 ft to the

    Jan 1, 1994

  • ISEE
    The Effect of Precise Millisecond Delay on Fragmentation at the Rock of Ages Quarry

    By Raymond H. Green, Mitchell W. Green

    The authors examined the application of precise millisecond delay electric blasting at a well-known Vermont quarry. The paper explains how the use of a new high-accuracy electric delay detonator has i

    Jan 1, 1986