    Vibro Stone Columns With Preloading – An Effective Foundation Solution For Large Storage Structures

    By Ramanathan C, Prasad P. V. S. R

    The most critical challenge for any large size storage structures to be constructed on soft compressible soils is bearing capacity and consolidation settlements. Consolidation is the time dependent ph

    Sep 1, 2022

  • DFI
    Single Pile Settlement Prediction And Analysis For Driven Piles

    By David R. Beadman

    The Fleming method is widely used for the analysis and prediction of single pile behaviour under maintained loading. The method does not distinguish between bored and driven piles. Driven piling avoid

    Jan 1, 2006

  • DFI
    Measurements of CDSM Strengths and Seepage Data Following Seismic Upgrades of San Pablo Dam

    By Atta B. Yiadom, A. David Miller, Robert C. Kirby, Sean M. Todaro

    "San Pablo Dam is a 170-foot (52-meter)-high earthfill embankment, located approximately 10 miles (16 kilometers) north of downtown Oakland, California, that impounds a 38,600 acre-feet (47.6 million

    Jan 1, 2015

  • DFI
    The Test on Effect of Polyanionic Cellulose on Process of Filtrate Loss of Low Solid-Phase Drilling Fluid (cdc8479e-b761-4427-8d26-4088be3d5ab5)

    By Ping Yang, Tian-bin Li, Min-hui Wu

    "The process of filtrate loss of low solid-phase drilling fluid at different content of polyanionic cellulose is investigated by the standard filtration test. The test results showed that when time of

    Jan 1, 2017

  • DFI
    Case Study: Load Transfer Analysis on an Instrumented Augercast Pile Using EDC Strain Gauges and Geokon Rebar Strainmeters

    By Sastry Putcha, Santosh Mummaneni, Swamy Avasarala, Vamshi Vemula

    "This paper presents the results from a case study on the comparison of two strain acquisition instrumentation technologies, Geokon rebar strainmeters and Embedded Data Collectors (EDC) for the DC Wat

    Jan 1, 1900

  • DFI
    Deep Soil Mixing Design and Construction for Surface Fault Rupture Mitigation

    By James R. Gingery, Byron Foster, Bret Lingwall

    While microzonation and setbacks are the typical mitigation for structures exposed to surface fault rupture hazards, lifelines and lifeline facilities are not easily relocated to avoid faulting. In th

    Sep 8, 2021

  • DFI
    Conventional Static And Rapid Load Tests On CIDH Piers At A University Of California Berkeley Site

    By Gyimah Kasali

    Rapid Load Testing was performed as part of an extensive drilled pier testing program for the University of California Berkeley Capital Improvement Program. The purpose of the program was to: (1)

    Jan 1, 2002

  • DFI
    Getting Paid In Hard Times - I. Formation Of The Contract

    By Dennis J. Riley

    A. This outline addresses what a sub-contractor, or a subsub-contractor should do to get paid in the event the general contractor or building owner files for bankruptcy. B. Negotiating payment ter

    Jan 1, 1991

  • DFI
    Construction Methods and Quality Outcomes for Bored Cast-in-Situ Piles – A Review of Current Practice

    By Jim Slatter, Ben Collingwood

    "It is well known that the adoption of an appropriate construction methodology is critical to quality outcomes for bored piles (drilled shafts). Many case studies have been published documenting quali

    Jan 1, 1900

  • DFI
    Rehabilitation Of Existing Foundation Piles Of Marine Structures In New York City Harbor, USA

    By P. B. Kelleher

    Most of the piers and other pile-supported marine structures in the New York City Harbor area were constructed prior to the widespread use of currently available pile protective systems. As a result,

    Jan 1, 1989

  • DFI
    Execution And Evaluation Of High Capacity Caisson Load Tests In Glacial Deposits

    By Franklin M. Grynkewicz

    As part of the Boston Harbor clean up project, the new 1,000 mgd Deer Island Sewerage treatment plant includes ten 240 feet high egg-shaped "residuals" tanks. Contract documents called for these struc

    Jan 1, 1992

  • DFI
    Piled Rafts: Are We Modelling Them Correctly?

    By Jonathan J. Dewsbury

    It is argued that approximate computer based methods are only suited to modelling conventional piled rafts, for pile enhanced rafts where the interactions will be non linear three dimensional finite e

    Jan 1, 2010

  • DFI
    Long-Term Performance Of Wind Turbine Foundations Through Numerical Modeling

    By Spencer Ness, Yazen Khasawneh, William Tjaden, Mohammad Nassim

    The evaluation of long-term performance of the wind turbine structures is essential in lowering the Levelized Cost of Electricity (LCOE) from wind sources. The required maintenance of the wind turbine

    Oct 1, 2022

  • DFI
    Case History On Pipe Pile Installation - Presented At An Associated Pile & Fitting Corp. GEO-Pile Conference San Francisco, CA

    By Jerry F. Parola

    In current practice, pile foundation design is based on a general under-standing of pile-soil interaction during installation and superstructure-pile-soil interaction after construction. The pile desi

    Jan 1, 1986

  • DFI
    World Financial Center Foundations, New York

    By G. Tamaro

    The World Financial Center is situated on a 60,000 square meter site at Battery Park City at the southern tip of Manhattan Island. The foundations for the buildings and the related infrastructure pose

    Jan 1, 1989

  • DFI
    Maturation of Risk Concepts in the Management of Infrastructure - Lessons from the US Army Corps of Engineers

    By Eric C. Halpin

    "1. Introduction and Backgrounda. In its fundamental form, risk is simply the likelihood of an adverse impact. Expanding on this theme, the Corps of Engineers has broadly defined risk associated with

    Jan 1, 2014

  • DFI
    Discussion On Base Grouted Piles

    By V. M. Troughton

    Further pile load testing has been carried out at Canary Wharf to compare the performance of base grouted and ungrouted bored piles founded in the Thanet Sand. The testing regime included three prelim

    Jan 1, 1991

  • DFI
    Ground Improvement by a Combination of a Mixed-In-Place (MIPTM) Lattice Grid Wall and Stone Columns to Mitigate the Risk of Liquefaction and Lateral Spreading

    By Noreen Tarac, Pablo Forgoso, Philipp Schober

    A multiple use storage facility building is being developed in the Philippines on a peninsula that was reclaimed in the 1990s without any soil treatment. The subsoil now consists of loose to medium de

    Sep 8, 2021

  • DFI
    Removal of the Former San Francisco-Oakland Bay Bridge Foundation Caisson E3 by Mechanical Means and Explosives

    By Michael Gebman, Jack Gerwick

    "With the opening of the new San Francisco-Oakland Bay Bridge East Span, the former bridge and its caisson foundations are being demolished. Caisson foundations are in the path of a future shipping ch

    Jan 1, 2016

  • DFI
    Construction And Stability Risks Of Fluid Supported Deep Excavations And Their Effects On Design Parameters

    By Martin D. Larisch

    The construction of diaphragm walls and most large-diameter bored piles (piers) is often carried out under drilling support fluids to temporarily stabilise the excavation prior to concrete placement.

    Nov 1, 2022