Recent Advances In Large Diameter Diaphragm Wall ShaftsBy Benoit Virollet
Over the last 10 years the diameter of unbraced, unlined and unanchored circular shafts has grown dramatically in many parts of the world. This progress has taken place through improvements in: constr
Jan 1, 2006
-
Single Axis Tooling Methods - A. IntroductionBy George K. Burke
Single axis soil mixing is a mechanical method of blending soil in situ with a reagent binder to achieve improved character. Generally this achieves a design compressive strength or shear strength and
Jan 1, 2001
-
Evaluating Geotechnical Resiliency Solutions in New York CityBy Karen C. Armfield, Gisele R. Passalacqua, Joanna Smith
When selecting a solution for improving resiliency at facilities, such as airports, utility and transit sites, there are many options to protect structures and equipment against potential flooding. Ea
Jan 1, 2018
-
Extrapolation of Unit Side Resistance in Drilled Shaft Foundations Based on Bi-Directional Load Test DataBy Ramin Motamed, Joseph A. W. Toth
Evaluation of the capacity of large-diameter drilled shafts using current load test methods present challenges when considering the magnitude of loads required to fully mobilize their capacities. Ofte
Jan 1, 2018
-
Experimental And Theoritical Studies On Pile Capacity - SynopsisBy K. Rambha Devi
The paper is an attempt to co-relate the findings of pile capacity using a number of formula suggested by various authors with the actual field load test results. Five locations consisting of wholly s
Jan 1, 1996
-
Wave Equation Analysis And Dynamic Monitoring - A Presentation At The Deep Foundations Institute?McGill University Symposium Montreal, September 1983By Bengt Fellenius
The conventional wave equation analysis without control of the representativeness of the parameters to the actual conditions does not provide accurate results. However, the representatives can be vast
Jan 1, 1984
-
Pile Design And Construction Challenges In Partially Thawed Alaskan SoilsBy John D. Thornley
Alaskan villages typically store a one-year supply of fuel to reduce significant delivery costs. Alaska Village Electric Cooperative (AVEC), an electric utility cooperative providing power to 51 Alas
-
Pile Design and Construction Challenges in Partially Thawed Alaskan Soils (f9ca4371-20bf-4196-a495-4aa1bd15a8c0)By John D. Thornley
Alaskan villages typically store a one-year supply of fuel to reduce significant delivery costs. Alaska Village Electric Cooperative (AVEC), an electric utility cooperative providing power to 51 Alask
Jan 1, 2017
-
Design Build & Failure: Perils at a High Risk Shoring and Retaining Wall Project.By Mark Spence, Tom Lardner, Matthew Janes
"IntroductionThe design-build method streamlines project delivery through a single contract between the Contract manager and the design-build team. The design-build method places emphasis on collabora
Jan 1, 2015
-
Uncertainties In CSL Test Interpretations And Recommendations Toward A More Efficient ProcessBy Rohrbach
Crosshole Sonic Logging (CSL) testing is commonly used to verify the integrity, quality and ultimately the acceptability of the concrete in structural elements such as drilled shaft foundations, secan
-
4 Equipment Installation: Recent Developments - Equipment Installation - Recent Developments: General Report On 'Deep Foundation Installation Monitoring' - 1. IntroductionBy B. De Paoli
At Pietrafitta, between Assisi and Perugia, ENEL (Italian National Electricity Authority) has for some time been managing a power-station operated with lignite, mined from an open mine on the way to e
Jan 1, 1994
-
Pile Load Test Results Using The New Statnamic MethodBy Matthew Janes
Quality control procedures are increasingly important with today's higher capacity foundations and complex loading conditions. The need for a mobile, repeatable, nondestructive and economical loa
Jan 1, 1990
-
Large Diameter Drilling Operations Of Multi Head Down The Hole Hammer Drill Through Boulders And Granite - Mach Drilling System And Some Construction ExamplesBy J. Nakayama
Construction of foundation piles or diaphragm walls through rocky or boulder containing formations has been long-standing difficulty. It has been widely understood that the down-the-hole hammer is t
Jan 1, 1989
-
DFI Mission Executed Through Growth of Micropile TechnologyBy Jim Bruce, Peggy Hagerty Duffy, Mary Ellen Large, Allen Cadden
"Over the past 40 years, Deep Foundations Institute (DFI) has executed its mission “to bring together multi-disciplined individuals and organizations to find common ground and create a shared vision a
Jan 1, 2017
-
Uncertainties in CSL Test Interpretations and Recommendations toward a More Efficient Process (d88ba311-8a75-4265-90f4-c083be22cd1a)By Mark A. Rohrbach, Timothy R. Kovacs, PhD Saidin
"Crosshole Sonic Logging (CSL) testing is commonly used to verify the integrity, quality and ultimately the acceptability of the concrete in structural elements such as drilled shaft foundations, seca
Jan 1, 2017
-
Pile Inspector's Guide To Hammers ? IntroductionThe pile inspector is a critical element in the quality control process necessary for a successful pile installation project. This guide is intended to provide the inspector with a basic understanding
Jan 1, 1995
-
Söderströmstunneln – An Immersed Tunnel Founded on Steel Core PilesBy Frank Haehnig, Kjell-Åke Averstad, Johannes Glückert
"AbstractThe Söderströmstunneln is part of the Citybanan project that is currently under construction in the centre of Stockholm. Main part of the lot Söderströmstunneln is a 300m long immersed tunnel
Jan 1, 2014
-
Prediction Of Settlement Of Structure With Piled-Raft Foundation Using Nodular PilesBy Koichi Kobayashi
Performance-based approach to design of structures including foundations was adopted after enforcement of the revised Building Standard Law in Japan in 2000. The use of piled-raft foundation is favora
Jan 1, 2006
-
A Tall Slender Tower Rises On Secant Piles and Drilled ShaftsBy Renzo D. Verastegui, T. C. Michael Law, Sitotaw Y. Fantaye, Alfredas Daugiala
"When completed, 520 Park Avenue will amend the Manhattan skyline and be one of the most prestigious high rise towers in New York City. The 52-story condominium building is located on a 60 by 100 feet
Jan 1, 2016
-
CFA Secant Piling In CaliforniaBy Philip Derbyshire, Dale J. Scheffler
"Continuous Flight Auger (CFA) piling is a variation of Augered Cast-In-Place (ACIP) or augercast piling. In both cases a continuous auger with a hollow stem is used to drill a hole and a pile is form