Building Above And Excavating Below An Iconic Building In ManhattanBy John S. Civetta, Seth Martin, Marc J. Gallagher, Arthur J. Alzamora, Ronald Peralta
The Crown Building, built circa 1921, is a 26-story iconic building located at West 57th Street and Fifth Avenue in the heart of Manhattan. The paper highlights collaboration between the geotechnical
-
Sheetpile Installation Vibration StudyBy Kenneth A. Pidgeon
This paper presents a case history on mitigating vibration problems associated with the installation of steel sheetpiles. The project in-cludes installation of steel sheetpiles for a utility trench wi
Jan 1, 1995
-
Construction Of Long Tubular Column Foundations Under Deep Water ? SynopsisBy C. L. Liao
The chief experiences for constructing deep tubular columns foundation under deep water are as follows: 1. P.C. tubular columns were sunk inside the caisson. 2. P.O. tubular columns of 3.6 M. diameter
Jan 1, 2010
-
Rock Socketed Drilled Shafts for the Goethals Bridge ReplacementBy John P. Turner, Steven S. Dapp, Dan A. Brown
"The Goethals Bridge Replacement (GBR) spanning the Arthur Kill Waterway between Elizabeth, NJ and Staten Island, NY consists of a dual-span 1,982.5-ft long cable-stayed bridge with approach spans of
Jan 1, 2016
-
A Ten-Year Perspective of Jet Grouting: Advancements in Applications and TechnologyBy Gary T. Brill
In the presentation, the development and new applications of the jet grouting technique in the North America are briefly introduced at first and followed by the outline and advantages of Jet Grouting.
Feb 10, 2003
-
The Waterloo Barrier - A Sealable Joint Steel Sheet Piling For Groundwater Control And Remediation - Presented At The Deep Foundations Institute Annual Meeting & Conference Toronto, Ontario, October 15-17, 1997 - SummaryBy Murray Gamble
A new type of groundwater cutoff wall has been developed at the University of Waterloo. The Waterloo Barrier? is a steel sheet piling system that incorporates a sealable cavity at each interlocking jo
Jan 1, 1997
-
Deep Compaction Of Saturated Loess By Means Of Sand-Gravel Piles ? SynopsisBy Z. G. Lin
In Xian, China, compaction by means of soil (or lime-soil) piles is one of the effective methods widely used for densifying loess and eliminating its collapsibility. However, as a result of groundwate
Jan 1, 2010
-
Large Scale Geotechnical Works on Norways Largest Infrastructure ProjectBy Brandon M. Robinson, Osman F. Besler, Dominik Gaechter
With the increase in population over the last decade, and anticipated population growth over the coming years, Norway is making significant investments in the Country’s infrastructure. Part of this in
Sep 8, 2021
-
Session 30 "Grouting for Tunnels 2"By Raymond Henn
Yes we have also used some however, again because of the nature of the maintenance window where we have that two hour (at best) window every night and due to the numerous other crews that are wanting
Feb 10, 2003
-
Analysis Of Driving Stress Measured In The RC Long PileBy Yu Zhenquan
At the construction site of Bao Shan Iron &. Steel Mill in Shanghai, lots of RC driven piles with length of 50 to 60m were applied. The most unfavourable distribution of stress along the pile shaft wa
Jan 1, 1991
-
Proposed Micropile Section for the 2006 IBCBy Lawrence F. Johnsen, Marc J. Gallagher
"Micropiles are small diameter, bored, grouted-in-place piles incorporating steel casing and/or reinforcements. The omission of micropiles from most United States building codes has resulted in the ap
Jan 1, 2005
-
-
Geophysical Methods for Site Characterization for Marine Foundations (2dc87bb8-7bfd-4523-92cd-c3dfe612556c)By Richard E. Sylwester
Evaluating surface and subsurface conditions for marine foundations (bridges, causeways, terminals, etc.) is often done with a limited amount of data. Subsurface information for these projects is prim
May 11, 2007
-
Extra Deep Cut-Off at 250 m Depth - A Case StudyBy Federico Pagliacci
"Many existing dams are subject to underwater seepage due to subsoil conditions, like deep alluvial deposits or pervious rocks or karst. Remedial works are necessary in order to install new cut-off wa
Jan 1, 2017
-
Integration Of Real Time Pile Design By Means Of Building Information ModelingBy Prof. Dr. -Ing. habil. Sascha Henke, Johannes Beck
The growth of Building Information Modeling (BIM) during recent years opens possibilities for integrating new digitally driven design approaches. While parametric design and algorithmic design slowly
May 1, 2022
-
Deep Mixing Technology: Comparison between Laboratory and Field Test Result, Different Jobsite Application.By Alessandro Bertero, Stefano Valagussa, Filippo Maria, Wesley Schmutzler, Leoni
"Abstract The Deep Mixing Method (DMM) represents a viable solution to improve the adverse geotechnical properties of foundation soils. Differences and the importance of performing pre-construction la
Jan 1, 2014
-
Mobilizing CIDH Pile Base Resistance on the Gerald Desmond Bridge Replacement Project with Tip GroutingBy Adam Zagorski, Rusty Lucido, Curt Scheyhing
"The current California Department of Transportation (Caltrans) practice based on AASHTO LRFD Bridge Design Specifications is to use the O’Neill and Reese method (FHWA, 1999) for calculating the side
Jan 1, 2017
-
Session 23 "Grout in Rock and Mining"By John Davie
We used a Remtek survey in Glenrock and had very good luck with it when we first started the initial investigation. We would have loved to have used that more but my understanding is the equipment is
Feb 10, 2003
-
Full-Scale O-Cell Load Test for a Rotator Drilled Rock Socket at the Main Span of the New Benicia-Martinez BridgeBy Ronnie X. Gu, Xing Zheng, Gem-Yeu Ma
Due to implementation of the rotator construction method from which a smooth shaft was anticipated, a full-scale pile load test (Osterberg Method) was performed at Pier 14 Pile 9 of the main span of t
Jan 1, 2005
-
Behavior Of Large Bored Piles With Grouted EndBy Zhang Yaonian
This paper describes full-scale tests on ten large bored piles with grouted end conducted for three projects in the urban area of Fuzhou city. Test program included site investigation, pile installati
Jan 1, 2004