Sleeved Pile Foundations For The W. Seattle - Harbor Islands Swing Bridge And The Seattle Access ProjectsBy Kent C. Werle
This brief discusses the installation and application of sleeved piles of two different types for two different projects, the W, Seattle to Harbor Island Swing Bridge Project and the Seattle Access Pr
Jan 1, 1990
-
Performance Of A Large Diameter Drilled Pier (f4c3f0c8-a45b-48d0-8d0a-138a34a08ce3)By A. J. Partos
The figures and tables referred to herein are presented in the Proceedings; Volume I, Pages 309 through 316. The 61-story One Liberty Place, at 315 m., is the tallest building 1n Philadelphia and
Jan 1, 1991
-
Maturation of Risk Concepts in the Management of Infrastructure - Lessons from the US Army Corps of EngineersBy Eric C. Halpin
"1. Introduction and Backgrounda. In its fundamental form, risk is simply the likelihood of an adverse impact. Expanding on this theme, the Corps of Engineers has broadly defined risk associated with
Jan 1, 2014
-
Comparative Analysis Between Traditional And EC7 Criteria Applied To The Design Of Diaphragm Walls Concerning The Ultimate Limit StatesBy J. Matos e Silva
The paper refers five examples of executed diaphragm walls with one to five levels of anchorages. For each example a comparison is made between the results of the design using the traditional crit
Jan 1, 2002
-
Deep Compaction Of Saturated Loess By Means Of Sand-Gravel Piles ? SynopsisBy Z. G. Lin
In Xian, China, compaction by means of soil (or lime-soil) piles is one of the effective methods widely used for densifying loess and eliminating its collapsibility. However, as a result of groundwate
Jan 1, 2010
-
St Joseph Hospital Of Bellingham, Washington Addition Supported On Helical Pulldown MicropilesBy J. L. Goen
The Saint Joseph Hospital of Bellingham is located on a site underlain by glacial outwash. The construction of a five-story tower addition above an existing two-story wing was supported by five large
Jan 1, 2004
-
The Waterloo Barrier - A Sealable Joint Steel Sheet Piling For Groundwater Control And Remediation - Presented At The Deep Foundations Institute Annual Meeting & Conference Toronto, Ontario, October 15-17, 1997 - SummaryBy Murray Gamble
A new type of groundwater cutoff wall has been developed at the University of Waterloo. The Waterloo Barrier? is a steel sheet piling system that incorporates a sealable cavity at each interlocking jo
Jan 1, 1997
-
-
High Strain Testing Of Augered Cast Piles At Miami Fort Power StationBy C. Michael Morgano
Static tests are costly and time consuming, so they are not always the best answer [ ]
Jan 1, 2005
-
Design Of The Foundation Of Zhu Jiang Fanying High-Rise Building Complex ? SynopsisBy A. F. Deng
A general description of the project, mainly the pier foundation design of the ZHU JIANG FANYING is presented in the paper. The major contents include the foundation scheme, the evaluation of bed-rock
Jan 1, 2010
-
An In-Situ Model Test For A Large Hydraulic Press Foundation ? SynopsisBy R. J. Yan
There was a plant equipped with a 32000t Hydraulic Press to be built, under which a box foundation of 22.5m x 15m x 14.25m (depth) with a base slab of, varying thickness was proposed. The subgrade rea
Jan 1, 2010
-
DFI Europe Monitoring and Instrumentation Committee ObjectivesBy Rob van Dorp
"AbstractThe Monitoring & Instrumentation Committee (MIC) of DFI Europe has the objective to support DFI members in concern of risk management of geotechnical matters, where monitoring and instrumenta
Jan 1, 2014
-
-
Contactless Anchor Measurement with Elastomagnetic SensorsBy Damir Dedic, Wörle. Patrick
"Soil properties within a construction project area are analyzed during the planning phase. However, it is only possible to achieve selective soil exploration, even in the case of very extensive inves
Jan 1, 2017
-
Technical Aspects And Research In DowndragBy Jean-Louis Briaud
The following is a summary of a very recent report prepared at Texas A&M University for the National Cooperative Highway Research Program and entitled "Downdrag on Bitumen Coated Piles". Anytime the
Jan 1, 1989
-
-
An Alternative Lower Carbon Footprint Foundation For A Large Oil Gas Project In Jurong Island, SingaporeBy Selvaganesh Selvaraju, Deepak Raj, Sandun N. Wimalasena
One of the world leading oil majors is carrying out a multi-billion-dollar expansion of its integrated manufacturing complex in Jurong Island, Singapore, the global oil trading and refining hub. Soil
May 1, 2022
-
General Reports - Session 1 - General Report- Deep Excavations "He Who Pays The Piper Calls The Tune"By Tim Chapman
This general report considers what promoters of deep basement projects want from their teams and whether they get it often enough. Most large projects are based on complex financial models where the f
Jan 1, 2006
-
Mission Valley Viaduct Piledriving - 1998 DFI Conference Seattle, Washington October 8, 1998By David A. Jack
The Mission Valley Viaduct is located in San Diego, California. This structure is the intersection of Interstate 8 and 805. The project consists of the main viaduct, 8 connecting ramps, and one highwa
Jan 1, 1998
-
Construction Of Large Drilled Shafts The 2nd Annual Mike O?Neill LectureBy Dan Brown