    Case History: Innovative Load Test Program Optimizes Pile Capacity in Challenging Ground Conditions

    By Emad Farouz, Francis A. Abreu

    "This paper presents a case history of a successful construction-phase pile load test program that optimized the pile design in challenging ground conditions at the Great Neck Wastewater Treatment Pla

    Jan 1, 2017

  • DFI
    Jet Grout For Soil Mass Stabilisation To Support Power Plant Foundation

    By Vishal Pathak, Shailesh A. Godhuly

    Ground Modification System in terms of Jet Grouting for soil strengthening and mass stabilization was engaged for a power plant project in an international power project, engineered by L&T-S&L. The si

    Sep 1, 2022

  • DFI
    Performance Based Excavation Support Design For Challenging Urban Site Geometry In Toronto, Canada

    By Shawna Munn, Carol Dounitch, Erika Acton

    The EQ Bank Tower, a 24-storey office tower with 4 levels of underground parking, is currently under construction at 25 Ontario Street in the downtown core of Toronto, Canada. The tower geometry requi

    Oct 1, 2022

  • DFI
    Sustainability Assessment of Deep Foundations: Case Study

    By Krishna R. Reddy, Jyoti K. Chetri, Girish Kumar

    Geotechnical engineering encompasses a major portion of the civil and infrastructure projects. The large amounts of energy and resources typically used in these projects leads to undesirable emissions

    Jan 1, 2019

  • DFI
    Performance Of Storage Tanks Supported By Shallow & Deep Foundations

    By Akhila Manne, Prasad P. V S R

    Storage tanks are heavily loaded thin-shelled structures that exert large loads on and require large foundations to support them. They are generally very sensitive to foundation settlements as it may

    Nov 1, 2022

  • DFI
    Geotechnical Assessment Of The Manhattan Cruise Terminal Piers: Analysis Of Timber Piles In Soft Organic Silts

    By Rodrigue Karam

    An assessment of the geotechnical conditions at the Manhattan Cruise Terminals (Piers 88, 90, 92 & 94) was conducted after excessive settlement and structural distress was reported at Pier 92. The pie

  • DFI
    A Review On Pedestal Piles

    By Venkatesh S. V J, Shubha M, Srilakshmi G

    Choosing for the best option of pile foundations to overcome large lateral and uplift loads for the foundations in transmission line towers/offshore environment is still being a concern to achieve the

    Sep 1, 2022

  • DFI
    Outstanding Issues In Understanding The Behaviour Of Thermally-Activated Pile Foundations

    By Teresa M. Bodas Freitas, Arianna Lupattelli, Peter J. Bourne-Webb, Diana Salciarini, Martina Zito, Donatella Sterpi

    The thermomechanical response of thermally-activated (TA) piles under monotonic thermal loads is quite well understood and the remaining uncertainties relate to the effect of long-term, cyclic loading

    May 1, 2022

  • DFI
    Using Settlement-Control Piles To Enhance Mat Foundation Of A High-Rise Building In Orlando

    By Amr M. Sallam

    A case history of utilizing a mat foundation enhanced with ?settlement-control? piles to support a high-rise building in Downtown Orlando is presented. Original geotechnical engineering studies, perf

    Jan 1, 2009

  • DFI
    Nailed It! The Great Wall of the Chinese Embassy (dbde4e01-35b2-40e7-b641-e07610069e96)

    By Fred Tarquinio, Giovanni Bonita, Lars Wagner

    "A new embassy for the Peoples Republic of China is under construction in Washington, DC. The 475,000 square feet (44,125 m2) structure has five levels below ground and four above, making it the large

    Jan 1, 2007

  • DFI
    Micropile Transmission Foundations In Environmentally Sensitive, Challenging Terrain

    By Esam Abraham

    A 13.6 mile portion of the 500 kV Tehachapi Renewable Transmission Project crosses the mountains of the Angeles National Forest. Access and environmental constraints precluded road development for mo

    Jan 1, 2010

  • DFI
    Foundation Design And Construction Challenges For The Phoenix Sky Train Project

    By John C. Niedzielski

    The PHX Sky Train is a five mile long automated people mover system located at Phoenix Sky Harbor International Airport. Phase I of the PHX Sky Train includes the design and construction of 227 drill

    Jan 1, 2010

  • DFI
    Construction Of The Main Tower Pier Caissons For The Greenville Bridge In Mississippi

    By F. Keith Jacobson

    To be involved in the construction of a deep dredged caisson for a major bridge pier is one of the most rewarding and professionally challenging experiences one can have in the bridge construction bus

    May 11, 2007

  • DFI
    Energy Geostructures: Analysis from Research and Systems Installed Around the World

    By Tony Amis, Marco Barla, Alice Di Donna

    "Energy geostructures are becoming an increasingly popular solution around the world for Developers looking to reduce CO2 and system running costs. Energy geostructures are geotechnical structures tha

    Jan 1, 2017

  • DFI
    Drilled Shaft Foundations for the Float-in Dam on the Monongahela River at Braddock, PA (6c19e969-5f09-43f8-9e6e-1837d4537e5e)

    By Robert B. Bittner

    The new gated dam on the Monongahela River at Braddock, Pennsylvania, was built for the US Army Corps of Engineers using an innovative "In-the-Wef' technology. A key feature of this technology in

    May 11, 2007

  • DFI
    Performance Analysis Of Fly Ash Stabilized, Highly Saline Unsaturated Expansive Clays: A Case Study

    By Mohini Patel, Jahnavi Parmar, Pranav R. T Peddinti

    Expansive clays pose a variety of geotechnical problems. Although the admixture stabilization is proven to address their problematic swelling and shrinkage characteristics, the influence of unsaturate

    May 1, 2022

  • DFI
    Alternative Design and Construction Method for Clinton CSO Underground Storage Facility

    By Meeok Kim, Paul Beljan, Gordon Chen

    "Clinton combined sewer overflow storage (CSO) facility project developed by the Department of Water Environment Protection of Onondaga County, New York, is to improve sewer facilities and infrastruct

    Jan 1, 2015

  • DFI
    Determination Of Hydraulic Conductivity Of The Coralline Limestone Aquifer Of Jeddah, Saudi Arabia: Precautions And Recommendations For Deep Foundations

    By Mohamed A. Eliwah

    This paper deals with the determination of hydraulic conductivity of the coastal coralline limestone aquifer of Jeddah, Saudi Arabia. This coastal area has witnessed urban development and establishmen

  • DFI
    Staged Construction of an Interstate I69 Embankment: Coupled Hydromechanical Numerical Simulation

    By Malek Smadi, Yazen A. Khasawneh

    "New embankments were constructed mostly on soft clays as part of interstate I69 extension in southern Indiana. The embankments serve as bridge abutments and as part of the fill sections along the int

    Jan 1, 2017

  • DFI
    Uncertainties in CSL Test Interpretations and Recommendations toward a More Efficient Process (d88ba311-8a75-4265-90f4-c083be22cd1a)

    By Mark A. Rohrbach, Timothy R. Kovacs, PhD Saidin

    "Crosshole Sonic Logging (CSL) testing is commonly used to verify the integrity, quality and ultimately the acceptability of the concrete in structural elements such as drilled shaft foundations, seca

    Jan 1, 2017