Plan compliance process for underground coal mines - SynopsisBy A. A. Angelov
This paper presents a unique method of monitoring the effectiveness of the planning process as well as the execution of mine plans. The method primarily determines the degree of deviation from the ori
Jan 1, 2010
-
A finite difference model of the iron ore sinter processBy J. C. Vreugdenburg, B. A. Dippenaar, J. Muller, T. L. de Vries
Iron ore fines are agglomerated to produce sinter, which is an important feed material for blast furnaces worldwide. A model of the iron ore sintering process has been developed with the objective of
Jan 1, 2015
-
The grate-kiln induration machine - history, advantages, and drawbacks, and outline for the futureBy J. C. Ion, O. Isaksson, J. Stjernberg
Iron ore pellets are a preferred feedstock for ironmaking. One method used for pelletizing is the grate-kiln process, first established in 1960.During the past decade, the establishment of new grate-k
Jan 1, 2015
-
3-D Numerical Modelling Of Stresses Around A Longwall Panel With Top Coal CavingBy N. E. Yasitli
There is a considerable amount of lignite reserve in the form of thick seams in Turkey. It is rather complicated to predict the characteristics of strata response to mining operation in thick seams. H
Jan 1, 2005
-
Sampling - A Critical Component To Gold Mining Project Evaluation (60ce14f9-844a-41ea-89be-138917950365)Poorly designed sampling protocols generally result in high project risk by artificially increasing grade variability (ie the nugget effect). Sample collection, preparation and assay protocols that su
Jan 1, 2007
-
Life And Design Of Bord-And-Pillar Workings Affected By Pillar ScalingBy M. D. G. Salamon
It has been noted in recent years that the pillars in some bord-and-pillar workings scale or spall. In due course this process may result in the collapse of the affected panels. This paper presents a
Jan 1, 1998
-
Equilibrium Interactions Between Freeze Lining And Slag In Ilmenite SmeltingIn ilmenite smelting, the FeO content of the feed material (nominally FeO.TiO2) is decreased by reduction with carbon. In a parallel reaction, a significant amount of the TiO2 is reduced toTi2O3. One
Jan 1, 2004
-
Design and Positive Financial Impact of Crush Pillars on Mechanized Deep-Level Mining at South Deep Gold MineBy B. P. Watson
Crush pillars have been incorporated into a mechanized, low-profile trackless system at South Deep Gold Mine. These pillars had to be designed to fail near the face and to ensure that pillar failure i
Jan 1, 2014
-
The role of gravity flow in the design and planning of large sublevel stopesBy M. Pineda
Sublevel stoping (SLS) is one of the oldest and most used methods for underground mining. It relies heavily on the use of drilling and blasting techniques to remove the rock, and gravity to transport
Jan 1, 2015
-
Design and development of a low noise rockdrillBy R. W. Ottermann, N. D. L. Burger, A. J. von Wielligh, P. R. de Wet, J. L. Steyn
A low noise blast hole drilling system was developed to limit the risk of noise induced hearing impairment in mining operations. Noise induced hearing loss has been identified as a major occupational
Jan 1, 2003
-
Breakeven Extraction Factors For The Merensky Reef Using Stope Width And Market Price SimulationBy M. G. Wimberger
The Merensky Reef zone, as developed on Impala Platinum?s Rustenburg Operations, displays a gradational mineralized zone, with grades decreasing from the Merensky Pegmatoid Unit into the footwall and
Jan 1, 2004
-
The Strategic And Tactical Value Of A 3D Geotechnical Model For Mining Optimization, Anglo Platinum, Sandsloot Open PitSandsloot open pit is situated on the northern limb of the Bushveld Complex, 250 km north east of Johannesburg, South Africa. Sandsloot is currently the largest open pit platinum mine in the world and
Jan 1, 2006
-
A Case Study Application Of Linear Programming And Simulation To Mine Planning - SynopsisBy J. A. de Carvalho Junior
This paper analyses the impact of the uncertainty associated with the input parameters in a mine planning optimization model. A real example was considered to aid in the building of a mathematical mod
Jan 1, 2012
-
Modelling water uptake in highly compacted bentonite in environmental sealing barriersBy W. Wittke, J. Gattermann
ABSTRACT: One alternative to close a radioactive waste repository in rock salt is the construction of a “Cross Section Closure (CSC)“ sealing barrier. The proposed material for the CSC is highly compa
Jan 1, 2003
-
Applications And Benefits Of 3D Laser Scanning For The Mining IndustryBy J. W. van der Merwe
Technology is advancing at a rate that makes it extremely difficult for the mining Industry to keep pace. Many advances occur within a given piece of technology and often this is missed by the discip
Jan 1, 2012
-
A heat transfer model for high titania slag blocks - SynopsisBy H. Kotzé
Titania slag is used as feedstock in the production of titanium dioxide pigment. It (titania slag) is the product of ilmenite smelting,a process whereby ilmenite is reduced at high temperature utilizi
Jan 1, 2010
-
Some Myths About DC Arc Furnaces ? SynopsisBy R. T. Jones
DC arc furnaces are widely used for steel scrap melting as well as for reductive smelting of ore fines. Industrial smelting applications include the smelting of chromite to produce ferrochromium, the
Jan 1, 2011
-
Focus On Platinum - The 8th International Platinum Symposium - Platinum Markets And ApplicationsBy D. T. G. Emmett
[ ] South Africa, by a wide margin, is blessed with the largest known world reserves of platinum. The optimal use of these resources for the benefit of all South Africa?s peoples is a goal shared by
Jan 1, 1998
-
Numerical simulation of multiphase flow in a Vanyukov furnaceBy Y. M. Chen, H. L. Zhang, W. U. Bing, C. Q. Zhou
Multiphase flow in the widely used Vanyukov furnace was numerically studied. An unsteady three-dimensional and three-phase flow model was firstly built using the computational fluid dynamics (CFD) sof
Jan 1, 2015
-
Quantitative Rockburst Hazard Assessment At Elandsrand Gold MineBy F. Essrich
A quantitative rockburst hazard assessment procedure was introduced on Elandsrand Gold Mine at the end of 1994. It is currently used to evaluate the seismicity-related risk in production areas on the