    Helical Piles With Grouted Shafts - A Case History

    By Shawn Downey

    A helical pile with in-situ grouted shaft was used to underpin the existing slab of a large retail store in the Edmonton, Alberta Canada area. The existing structural slab did not have the capacity to

    Jan 1, 2003

  • DFI
    Trencher Method Vs. Slurry Trenching: A Pros & Cons Comparison Of Case Studies

    By Daniel Ruffing, Charlie Krug

    In recent years, the chain-style trencher has been proven a valuable tool for installing vertical walls on challenging sites where conventional methods may be less desirable. Like many tools, trencher

  • DFI
    Depth Of Borings, Length Of Piles, Landslides, Erosion, And A Moose Hunt - A Case History Of A Comedy Of Mistakes

    By Bengt H. Fellenius

    An upgrading and straightening of a highway included building a bridge across a small river. A routine site investigation was initiated to determine the conditions for designing the foundation of the

    Jan 1, 1987

  • DFI
    Settlement Control Of A Road Embankment Using Vertical Drains

    By Wei Tu

    A grade separation was required to allow uninterrupted traffic crossing for a busy rail spur and a county road. The grade separation was achieved by creating a 30-foot (9-meter) high embankment that

    Jan 1, 2009

  • DFI
    Berth Deepening A Three Decade Old Wharf Structure For The Next Generation Of Container Ships

    By Bill Paparis

    The thirty year old wharf structures at the Port Authority of New York & New Jersey?s Port Elizabeth Marine Terminal are being modernized for the next generation of Post-Panamax container ships, which

    Jan 1, 2013

  • DFI
    Theory And Practice Of Pile Foundations ? Synopsis

    By G. G. Meyerhof

    The paper reviews the state of the art of estimating the bearing capacity and settlement of pile foundations in sand and clay soils, including the effects of pile installation, scale effects of pile s

    Jan 1, 2010

  • DFI
    Investigation Of Bearing Behavior Of Pile Raft Foundation Using Numerical Modeling

    By A. Ghorbani

    The analysis of Combined Pile Raft Foundation (CPRF) is very complex due to involved interactions among components of CPRF system. Many researchers made efforts to develop sufficient methods including

    Jan 1, 2007

  • DFI
    Reliability Approach For Deep Foundation Studies ? Synopsis

    By R. Chowdhury

    The relevance of reliability studies for deep foundations is considered in this paper with special reference to pile foundations. Attention is drawn to uncertainties related to applied loads, the load

    Jan 1, 2010

  • DFI
    Implementation Of Alternative Deep Foundation Systems

    By Ray Zelinski

    Caltrans sponsored a research project in 1992 which incorporated proprietary and generic pile types. The piles were subjected to axial tensile/compressive loads in deep, soft soils. Descriptions of va

    Jan 1, 1993

  • DFI
    Multiple Foundation Types For Bridges Over The Same Coal Mine

    By Kenneth M. Berrry

    A unique situation has developed at an abandoned coal mine in St. Clair County, Illinois. Subsidence features have been observed at the ground surface over the mine including settlement of a pair of b

    Jan 1, 2001

  • DFI
    Non-Destructive Testing Of Piles - A Case History - Summary

    By Manish Kumar

    One of the recent advances in the field of testing of concrete piles is the Non-Destructive testing (NDT) of piles. This paper deals with a specific project where this technique was employed along wit

    Jan 1, 1996

  • DFI
    Design Method For Bridge Abutment Foundation Piles Subjected To Lateral Earth Pressure ? Synopsis

    By T. Matsui

    Many existing bridge abutments on the soft ground laterally move and their many damage examples have been reported. An essential cause for the troubles of the lateral movements may be the lack of exam

    Jan 1, 2010

  • DFI
    St. Anthony Falls, I-35w Bridge Drilled Shaft Load Test Program

    By Jeffrey A. Gebhard

    As part of the design and construction of the new St. Anthony Falls I-35W Bridge, a full-scale load test was conducted on a 6 1/2-foot diameter drilled shaft in the St. Peter Sandstone. This load tes

    Jan 1, 2009

  • DFI
    Selection And Design Of Continuous Flight Auger And Drilled Displacement Piles

    By Dan Brown

    This paper provides an overview of the advantages and limitations of continuous flight auger (CFA) and drilled displacement (DD) systems compared to other deep foundation systems, along with a summary

    Jan 1, 2005

  • DFI
    2D And 3D Ansys Modeling For Deep Excavation And Evaluation Of Soil-Structure Interaction

    By Yahia M. Al-Smadi

    Effect of lateral loading against existing sheet pile wall and distribution of gravity loading due to various number of construction loading scenarios were studied. The objective of this effort was t

    Jan 1, 2010

  • DFI
    St. Anthony Falls I-35W Bridge - Deep Foundation Monitoring Methods And Equipment For Bridge Construction

    By Bryan C. Field

    The proposed construction schedule for the St. Anthony Falls I-35W Bride challenged the abilities of the design-build teams to utilize the best and most efficient methods to meet Minnesota Department

    Jan 1, 2009

  • DFI
    Installation Checklist For Driving Mega Piles

    By Douglas L. Scaggs

    Over the past several years, pile foundations have grown to meet the demands of larger and heavier structures. As the foundations have grown, so has the need for larger and more robust piles to carry

    Jan 1, 2013

  • DFI
    Modeling Of MSE Wall - Drilled Shaft Systems

    By Matthew C. Pierson

    Due to space limitations for transportation projects, many times sound walls must be constructed above mechanically stabilized earth (MSE) walls. These sound walls must resist lateral loads from wind

    Jan 1, 2009

  • DFI
    Drilled Piers Support Massive Gantry Crane

    By John R. Davie

    This paper describes the design and construction of two 5.6 MN capacity drilled piers installed to support the main loading elements of a large cantilevered gantry crane. The critical crane columns we

    Jan 1, 2006

  • DFI
    Structure Monitoring During Underpinning

    By Barry C. Roth

    A Real Time Automated Remote Reading Electrolytic Tilt Monitoring System was effectively deployed for monitoring an existing five story brick building during underpinning, shoring and excavation opera

    Jan 1, 2007