    Hydraulic Calculation of Gravity Transportation pipeline System of Cemented Coal Gangue Backfilling in Suncun Coal Mine, China

    By Q. Zhang

    The necessary capability of the gravity transportation pipeline system for cemented coal gangue backfilling at the Suncun Coal Mine, China, is about 74.4 m3?h-1 according to mining production and work

    May 1, 2007

  • CIM
    Pipe Ore Processing Developments in the Thompson Mill

    By P. G. Claridge, R. A. Tenbergen

    "Pipe Open Pit ore is delivered by rail to the Thompson Mill at a rate of 34,000 tons per week. Ore is milled at a rate of 220 tons per hour.Characteristics of the serpentinised peridotite host rock a

    Jan 1, 1975

  • CIM
    Failure Mechanisms of Pillars Under Shear Loading

    By Joseph J. Mgumbwa

    Pillars are any structures left between two or more underground openings. The stability of pillars is normally considered to depend on shape (defined by width to height ratio), rock mass strength, ext

    Oct 1, 2010

  • CIM
    The Polaris Process Barge (413f976a-6a5f-4235-9531-1db4119721bb)

    By J. K. Gowans

    "INTRODUCTIONTo bring a mining property into production in the Canadian High Arctic a company must deal with the harsh environment, the short shipping season and the high cost of labour. In trying to

    Jan 1, 1983

  • CIM
    Latest Fire Protection Innovations for Large-Scale Mining Equipment

    By Don A. Toth

    Until recently, the fire protection systems used to protect mining equipment were based on generically designed, off the- shelf concepts. These systems were reliant on single agent approaches and were

    Apr 1, 2005

  • CIM
    Investigation of Liner Wear at Chadormalu Semi-autogenous Grinding Mills

    By Mohammad Noaparast, Babak Fotoohi

    "Due to certain advantages in (semi-)Autogenous-Ball mill circuits in most of the high-throughput ore grinding units of mineral processing plants, much attention is paid to optimize the mill performan

    Jan 1, 2005

  • CIM
    Optimization of the Damang Mine (f1135579-fc96-4b0b-98ae-1df94fee7413)

    By Dayang Datu Khalil, Charle Amoah, Fred Kock

    Abosso Goldfields Limited has been optimizing the comminution circuit at the Damang Mine Operation for the treatment of 100% primary ore. The optimization process started at a base rate of 343 tph whe

    Jan 1, 2012

  • CIM
    The Niobec Mill

    By Michel Robert

    "In 1974, Copperfields Mining Corporation and Soquem formed a new company, Niobec Inc, to bring the niobium deposit of the St-Honore carbonatite into production.St-Honore is located in the Saguenay ar

    Jan 1, 1978

  • CIM
    A Microstructural Study of the Fatigue and Dwell-Fatigue Behaviour of ATI 718plus® Alloy

    By S. Oppenheimer, P. Au, R. M. Kearsey, J. Tsang, E. McDevitt

    A new superalloy, ATI 718Plus® Alloy (718Plus), has been developed to have a 55oC higher temperature capability over the traditionally used Alloy 718, while maintaining favourable processing character

    Jan 1, 2010

  • CIM
    Cyanide Recovery and Copper Removal from Gold Plant Effluents using Vitrokele™ - Pilot Plant Results

    By D. Kidby, A. Briggs

    "Vitrokele ™ is a synthetic adsorbent, using chelating groups on large polystyrene beads, developed in Canada over 7 years ago, and first commercialised in 1985 to recover noxious metals from plating

    Jan 1, 1992

  • CIM
    The Kumtor Gold Mill Start Up and Start up Challenges

    By John Kazakoff, Andrew Mortimore

    "Production at the remote Kumtor Gold Mine in Kyrgyzstan commenced on schedule in December 1996.The ore mined during the first few months of 1997 from the upper benches of the pit did not produce the

    Jan 1, 1999

  • CIM
    Reducing Selectivity in Narrow-Vein Mining through the Integration of Underground Pre-concentration

    By Andrew Bamber

    The introduction of pre-concentration technology into the underground narrow-vein mining scenario has the potential to change the entire economics of utilizing bulk-mining methods in these situations.

    Oct 1, 2004

  • CIM
    Cluff Lake Mill - Phase 2 Expansion

    By H. A. Schnell

    "The Phase I Mill at Cluff Lake in northern Saskatchewan was designed to accommodate a very specific high grade uranium ore. As this high grade ore was depleted, construction was undertaken on a new m

    Jan 1, 1985

  • CIM
    Modelling Secondary Crushing Plants for Teaching Purposes and Operator Training

    By J. A. Meech, R. J. Tucker

    "A dynamic computer model has been developed to simulate the operation of ore crushing plants. The model was created in a general form to allow imitation of a wide variety of secondary crushing circui

    Jan 1, 1985

  • CIM
    Goldcorp Inc., Red Lake Mine Design and Commissioning

    By R. Tyreman, G. Ritson

    "The Red Lake Mine is situated in Balmer Township, Red Lake area in northwestern Ontario. It is an underground mine that has been in production since 1948. The property was originally known as the Dic

    Jan 1, 2001

  • CIM
    Condition Monitoring and Basic Maintenance?. One Without the Other?

    ? Founded In 1953 ? Mining growth of 83% since 2007 ? We produced over 1 million ounces of Au in 2012 ? We Forecast of 20% Au production in 2013-2015 ? We have paid a dividend 31 years consecuti

    Aug 1, 2013

  • CIM
    Circuit Consolidation at Pine Point Mines Limited Pine Point, N.W.T.

    By R. E. Jones

    "INTRODUCTIONCominco Limited, one of the free world's largest producers of lead and zinc having majority ownership in Pine Point Mines Ltd., operates a mining and concentrating complex on the south sh

    Jan 1, 1982

  • CIM
    High Pressure Direct Injection of Natural Gas in a Diesel Engine for High Performance/Low Emissions

    By K. Bruce Hodgins

    The North American mining industry faces challenging emissions regulations in coming years with the introduction of new standards for off-road diesel engines. In order to remain competitive, industry

    May 1, 2002

  • CIM
    Pressure Acid Leaching of Non-Ferrous Smelter Slags for the Recovery of Their Base Metal Values

    By W. Curlook, V. G. Papangelakis, M. Baghalha

    A pressure acid leaching process has been developed for the extraction of metal values, nickel, copper, cobalt and zinc, from base metal smelter slags. The basic concept contemplates cooling the smelt

    Jan 1, 2004

  • CIM
    Converting the Key Lake Mill Process for McArthur River Ore

    "The Key Lake mill was commissioned in 1983 to process the two Key Lake ore deposits. With the depletion of these ore bodies in 1999, the plant was converted to mill the exceptionally rich McArthur Ri

    Jan 1, 2001