  • AUSIMM
    Integrated Expert Control System for Grinding and Flotation

    By Jarvensivu M, Ylinen R, Jamsa-Jounela S-L

    The paper presents a new integrated system for control of concentration processes. The system is based on cluster-based modelling taking the ore quality into account and a new on-line particle size

    Jan 1, 1993

  • SAIMM
    Integrated Furnace Controls: Implementation On A Covered-Arc (Shielded Arc) Furnace At Cerro Matoso

    By T. Gerritsen, R. C. Delgado, J. Janzen, E. R. Veloza

    The paper describes the components of an Integrated Furnace Control system for covered-arc (shielded arc) smelting with results from the recently started 75 MW Cerro Matoso Line 2 Furnace. The paper s

    Jan 1, 2004

  • CIM
    Integrated Grinding and Flotation Simulations for the Improvement of Circuit Performance at BHP-Billiton’s Minera Escondida

    By H. E. Urtubia, C. W. Bailey

    "BHP-Billiton’s Minera Escondida Limitada is one of the world’s largest copper producers. It treats a combined 88 million tons of copper ore per year through its two concentrators: Los Colorados and L

    Jan 1, 2007

  • SME-ICGCM
    Integrated Instrumentation Method of Stress State, Material Property, and Deformation Measurement for Stress Control Method of Mining

    By Shosei Serata

    The application of conventional rock mechanics methods to complex ground is very difficult. Yet. In most underground mining, the ground is complex. Therefore. conventional methods are not only difficu

    Jan 1, 1986

  • AUSIMM
    Integrated Maintenance Services at the Los Pelambres Mine in Chile - The Lessons Learnt and Best Practices Developed from a Long-Term Sustainable Relationship

    By L Avalos, F Melo Miranda, J Misle, M Ingwersen

    "Los Pelambres, majority owned by the Chilean company Antofagasta Minerals, is one of the leading producers of copper and molybdenum in the country. It is located high in Andes Mountains, over 3000 me

    Jul 15, 2013

  • AUSIMM
    Integrated Management in the Mining Industry

    If you are to be and remain competitive in the mining industry, it is vital that your company management systems are efficient. An integral part of today's competition in a ruthless market is to

    Jan 1, 1997

  • AUSIMM
    Integrated Mine Evaluation ù Implications for Mine Management

    By M Armstrong, S J. Coward, A Galli

    Mine management is often expected to make rapid evaluation decisions at different stages of projects based on limited and uncertain data. The challenge is exacerbated by having to distil technical com

    Jan 1, 2006

  • SME
    Integrated Mine Production - The Key To Increased Production And Cost Control

    By F. Carew

    Accurate knowledge of what mass and grade is to hand and where it is stored is key to mine efficiencies and overall profitability. In order to make the right decisions and align production with stockp

    Jan 1, 2011

  • AUSIMM
    Integrated Mining and Metallurgical Planning and Operation

    By P L. McCarthy

    To design and operate a successful mine the technical specialists must agree on what is ore, what is not ore, and how quickly the orebody is to be mined and processed. These seemingly simple questions

    Sep 7, 2015

  • CIM
    Integrated Modelling of Subsidence Mechanisms and Impacts Due to Mine Caving

    By C. O?Connor

    With ever-increasing global demand for mineral resources, numerous mines are moving towards developing and mining deeper, more complex and lower grade ore bodies. In many cases, mass mining methods (e

    May 1, 2007

  • CIM
    Integrated Operations for Maximizing Results

    By D. Schleiss

    Reduced access to knowledgeable workers is creating challenges for operations. We are doing more 4D Operations - dirty, dull, dangerous, and distant. Personnel costs in these environments are high, an

    Jan 1, 2014

  • SAIMM
    Integrated Optimization Of Underground Mine Design And Scheduling

    By J. Little

    It is common practice for underground mine plans to be created sequentially, where results from one planning process form the input data for another. While this is practical for manual methods, comput

    Oct 1, 2013

  • CIM
    Integrated Pit-to-Port Planning, Optimisation and Delay Accounting

    The Challenges in Mining _Large expensive assets that are not being utilised as well as they should _?Silo? operations plan, schedule and execute in isolation?poor visibility across the Value Chai

    Nov 1, 2011

  • SAIMM
    Integrated Short- And Medium-Term Underground Mine Production Scheduling - Synopsis (01060c16-86e0-4e0e-8e87-e1ba1c275054)

    The development of short- and medium-term mine production schedules in isolation from each other has meant that only a local optimum can be achieved when each scheduling phase is carried out. The glob

    Jan 1, 2012

  • SME
    Integrated Sustainability Assessment in the Mineral Industry - Framework and Example

    By R. J. Baumgartner

    Sustainability issues are from rising interest and importance for the mineral industry worldwide. In order to bring them into management processes and to improve decision processes, economic, ecologic

    Jan 1, 2005

  • CIM
    Integrated Underground Mining and Processing Of Massive Sulphide Ores

    By Bern Klein, Malcolm Scoble, Justin Widdifield, Andrew Bamber

    "It has been suggested that the pre-concentration of ore underground can bring positive economic and environmental benefits to underground mining, particularly at extreme depth. The integration of min

    Jan 1, 2006

  • AUSIMM
    Integrated Utilisation of Desulfurisation and Skimming Slag

    Integrated Utilisation of Desulfurisation and Skimming Slag

    Sep 13, 2010

  • AUSIMM
    Integrated Whaleback Planning and Scheduling System

    Various software packages are discussed. These are components of an Integrated Planning and Scheduling System developed by MVM with the aim of providing up-to-date information for the Whaleback o

    Jan 1, 1986

  • AUSIMM
    Integrating Bulk Ore Sorting into a Mining Operation to Maximise Profitability

    By P Holtham, K Duffy, W Valery, A Jankovic

    As high grade ore deposits are depleted, remaining deposits are generally lower grade and require the mining and processing of larger volumes of material per tonne of product. These low grade deposits

    Sep 7, 2015

  • SME
    Integrating Community Capacity Building And Reuse Planning Into The Reclamation Of American Mine-Lands: How U.S. Regulators Are Cleaning Up With Communities

    By K. A. Larsen, J. L. Ariail, C. M. LaRosa

    This article discusses the evolution of U.S. laws and policies towards environmental remediation at mine lands over the last 20years, the opportunities that these changes present for reuse, and the re

    Jan 1, 2004