    The Development of Mining Geology in the Sudbury District

    By H. F. Zurbrigg

    Introdduction The main line of ascent in the development of the nickel industry may be traced back through the International Nickel Company of Canada, Limited, to its earliest antecedents, the Cana

    Jan 1, 1948

  • AUSIMM
    Statistical Analysis of Sampling and Assaying Results, Drilling Campaign, King Island Scheelite Mine, Tasmania

    During the drilling campaign conducted between October, 1942; and May, 1943, to prove the extent of the scheelite deposit worked by King Island Scheelite N.L. at Grassy, King Island, Tasmania, 35 hole

    Jan 1, 1950

  • IOM3
    Influence of a pisolitic limonite on sintering of an Australian iron ore blend

    Studies were carried out to examine the effect of introducing varying levels of a pisolitic limonite (Yandi) into an Australian iron ore blend. Compared with other ores in the blend Yandi is more poro

    Dec 1, 1991

  • NIOSH
    IC 7743 Mining Methods And Costs At The Morning Mine, American Smelting & Refining Co., Shoshone County, Idaho - Introduction And Summary

    By John R. Reynolds

    This paper describes mining and milling methods of the American Smelting & Refining Co. at the Morning mine in the Mullan area of the Coeur d'Alene mining region in Idaho and is one of a series o

    Jan 1, 1956

  • DFI
    Micropile Foundation Retrofit Design For Richmond-San Rafael Bridge, Richmond, California - Introduction

    By Patrick E. Durnal

    The Richmond-San Rafael Bridge was built in the early 50s' and was first opened to traffic on August 31, 1956. Among California's longest steel bridges, it spans more than 21,000 feet across

    Jan 1, 1998

  • SME
    Improvements in Plant Scale Nitric-Sulfuric Acid Pressure Leaching of Refractory Sulfide concentrates

    By Corby G. Anderson

    Since 1985, the Sunshine Mining Company has used a patented nitric-sulfuric acid pressure leaching system for production of silver and copper from a refractory sulfide ore body. To better understand t

    Jan 1, 1991

  • DFI
    A Study Of Three Test Sites Comparing Theoretical Ultimate Pile Capacities, Static Pile Load Tests, And Psuedo Static Pile Load Test Results

    By Richard D. Short

    The Pseudo Static Pile Load Test, PLT, is a rapid method for determining pile capacity. Pile design is usually based on theoretical calculations of ultimate load capacity using soil data from a field

    Jan 1, 2000

  • SME
    Cross-Borehole Geophysical Probing For Site Characterization

    By R. J. Lytle

    INTRODUCTION Prior to excavation in soil and rock, it is useful to know the subsurface structure. This is important information both for safety and for equipment scheduling reasons. It is useful to

    Jan 1, 1979

  • DFI
    The Type Of Wharf Structure On Soft Soil With Undulating Weathered Rock Bed

    By Sun Shao Xian

    The Port of Shekou is situated at Shenzhen Bay on the east side of the Pearl River estuary. Geological condition of the site is quite complicated. On top of the sea bed, there is a layer of soft silt

    Jan 1, 1991

  • SME
    Ecosystem Restoration Within The Anchor Hill Pit Lake, Gilt Edge Mine Superfund Site, South Dakota

    By J. Jonas, J. M. Harrington, K. Wangerud, S. D. Fundingsland, J. G. Harrington

    EPA NRMRL Mine Waste Technology Program and Region VIII Superfund office are jointly conducting an in-situ technology demonstration at the Anchor Hill Pit Lake, Gilt Edge Mine Superfund site. The goal

    Jan 1, 2004

  • DFI
    Elimination Of Heave Forces On Lightly Loaded Piles In Swelling Clay - Summary

    By Basem Sh. Hazzan

    In the last four decades significant effort has been devoted to designing piles in expansive clay soils. Nevertheless, only a scant effort has been devoted to the elimination of heave forces acting on

    Jan 1, 1999

  • AUSIMM
    Improvements in Flotation Cell Maintenance, Power Consumption and Operation at South32 Cannington

    By M Bird, B Oats, M Sganzerla

    Mining operations are continually aiming to reduce operating costs to improve plant profitability. One way in which the Cannington operation sought to achieve this was by increasing the wear life and

    Sep 7, 2015

  • IOM3
    Liquid-phase mass transfer in top-blown open-channel flows

    By N. A. Warner, R. K. Manna

    Physical modelling of liquid-phase oxygen mass transfer in a water model of part of a proposed new polymetallic smelter has been achieved. A study of solute mass transfer caused by multiple, subsonic

    Jul 1, 1991

  • DFI
    RD Pile Wall – A Water Tight Retaining Wall Structure

    By Antti J. Perala, Teemu J. Yli-Kovero

    "Efficient use of land is constantly requiring more underground construction. Minimized execution time and disturbance to surroundings and nearby structures are essential benefits for all construction

    Jan 1, 2017

  • TMS
    Closed Loop WEEE Recycling? Challenges and Opportunities for a Global Recycling Society

    By C. E. M. Meskers

    End-of-life Electronic and Electrical Equipment, o_cially called WEEE, is unjustly regarded as mainly a waste management problem. What is structurally overlooked is the enormous resource impact of the

    Jan 1, 2009

  • CIM
    High Fidelity Simulation of Full Mill Transport and Breakage in SAG/AG and Pebble Mills

    By John A. Herbst, Alexander Potapov, Xiangjun Qiu

    "High Fidelity Simulation is a name applied to the use of first principles modeling tools including Discrete Element Modeling (DEM), Computational Fluid Dynamics (CFD) and Discrete Grain Breakage (DGB

    Jan 1, 2003

  • CIM
    Model Predictive Control of the Flotation Process

    By Donald Leroux, Martin Suichies, Andy Trusiak, Chris Dechert

    "In modem concentrators, the operation of flotation machines is often stabilized by simple control loops. Froth level, slurry density and aeration rate are all physical parameters typically controlled

    Jan 1, 1999

  • NIOSH
    OFR-105(2)-84 Ground And Air Vibrations Caused By Surface Blasting. Volume 2 Ground Vibration Monitoring And Assessment Of Conventional Predictors

    By Sally A. Shoop

    Thirty-seven blasts have been monitored using either three or four seismographs, at four coal strip mines and at a limestone quarry. Statistical analysis of the data shows that square-root, cube-root,

    Jan 1, 1983

  • ISEE
    Wave Interference Attenuation Relationships and Prediction

    By Kimberlee Falkenstein, Volha Kibitkina, Jessica Steeves

    A series of experiments were conducted to obtain site specific constants for the vibration produced by a single charge and by more charges detonating in sequence, using short delay intervals. All char

    Jan 1, 2013

  • DFI
    Piling The Gateway To Europe

    By Howard Roscoe

    Linking Ashford International Station to the new Channel Tunnel Rail Link required over 5000 rotary bored and CFA (continuous flight auger) piles to form tunnel walls and viaduct foundations and to su

    Jan 1, 2002