    Design of the Epping to Chatswood Rail Line, Sydney, Australia

    By Jim Rozek, Robert A. Gee

    The Epping to Chatswood Rail Line project is the largest publicly funded infrastructure project in New South Wales. Construction commenced in November2002 with opening scheduled for 2008. The work inc

    Jan 1, 2005

  • DFI
    Design Of The Foundation Of Zhu Jiang Fanying High-Rise Building Complex ? Synopsis

    By A. F. Deng

    A general description of the project, mainly the pier foundation design of the ZHU JIANG FANYING is presented in the paper. The major contents include the foundation scheme, the evaluation of bed-rock

    Jan 1, 2010

  • AIME
    Design Of The Geologic Program At The Zortman And Landusky Mines, Little Rocky Mountains, Montana

    By M. S. Enders, L. M. Rogers

    The Little Rocky Mountains host epithermal gold-silver bearing vein and stockwork deposits in a syenite intrusive complex. Pegasus Gold Ltd. is currently mining these oxidized deposits by open-pit met

    Jan 1, 1984

  • SME
    Design Of The Geologic Program At The Zortman And Landusky Mines, Little Rocky Mountains, Montana

    By M. Stephen Enders

    The Little Rocky Mountains host epithermal gold-silver bearing vein and stockwork deposits in a syenite intrusive complex. Pegasus Gold Ltd. is currently mining the oxidized deposits by open-pit metho

    Jan 1, 1983

  • SME
    Design of the High Capacity, Horizontally Curved Overland Conveyor at Batu Hijau

    By Philip K. Chan

    Batu Hijau is a new copper and gold mine located on the island of Sumbawa in the Republic of Indonesia. This paper details the design and construction of the Batu Hijau overland conveyor, one of the m

    Jan 1, 2000

  • CIM
    Design of the jointed roof in stratified rock based on the voussoir beam mechanism

    By P. Mottahed, J. Ran

    Mining practice and research have shown that the jointed roof in stratified rock behaves like a voussoir beam structure with strength greater than that determined by the continuous beam theory. Previo

    Jan 1, 1995

  • CIM
    Design of the Kubaka Grinding Circuit Using SPI and Bond

    By Graham Holmes, John Starkey

    "The Kinross Kubaka Project is a gold mine located in the Russian Far East. The grinding circuit, comprised of a 6.1 m diameter x 2.74 m long SAG mill and a 4.1 m diameter x 5.5 m long secondary ball

    Jan 1, 2001

  • AIME
    Design of the Leadville Concentrator

    By Donald E. Crowell

    Due to falling metal prices and depletion of ore reserves, lead- zinc mining in the Leadville, Colo., area gradually came to a halt in the 1950's. Exploration work continued, however, and by 1969

    Jan 11, 1972

  • SME
    Design Of The Leadville Concentrator

    By Donald Crowell

    Due to falling metal prices and depletion of ore reserves, lead-zinc mining in the Leadville, Colorado, area gradually came to a halt in the 1950's. Exploration work continued, however, and by 19

    Jan 1, 1972

  • AIME
    Design of the Leadville Concentrator (TRANSACTIONS - VOL. 254)

    By Donald E. Crowell

    In the fall of 1969, ASARCO and Newmont Mining Co. began the design of the 700tpd concentrator at their Black Cloud shaft located near Leadville, Colo. The concentractor would treat by flotation a Pb-

    Jan 1, 1974

  • DFI
    Design of the Lift-in Dam at Olmsted on the Ohio River

    By Dale E. Berner

    A new navigation dam at Olmsted on the Ohio River will be built "in-the-wet" using a lift-in construction method by the Washington Group/Alberici Joint Venture for the U.S. Army Corps of Engineers, Lo

    May 11, 2007

  • DFI
    Design Of The Marine Foundation For The Skyway Project Of The San Francisco Oakland Bay Bridge

    By Gerry Houlahan

    The east span of the 3.5 km long SF-Oakland Bay Bridge is supported by different types of foundations along its span. Starting from the west, its first 460 m section comprising twin concrete box-girde

    Jan 1, 2005

  • DFI
    Design Of The Marine Foundations For The Skyway Project Of The San Francisco Oakland Bay Bridge

    By Gerry Houlahan

    The east span of the 3.5 km long SF-Oakland Bay Bridge is supported by different types of foundations along its span. Starting from the west, its first 460 m section comprising twin concrete box-girde

    Jan 1, 2013

  • AUSIMM
    Design of the Melbourne City Link Tunnels

    By S Porter, R Woodall, N Weeks

    Nelsen, Porter and Wilson (1996) provided some preliminary concepts for the design of the Melbourne City Link tunnels. At that time, the City Link project was in the early design phase whereas now it

    Jan 1, 1999

  • CIM
    Design of the New Lihir Gold Pressure Oxidation Autoclave

    By M. J. Collins, B. Parekh, A. Hasenbank, B. Hewitt

    Newcrest Mining Limited, originally as Lihir Gold, has operated a pressure oxidation plant for the recovery of gold from refractory ore since 1997. The mine and gold plant are located on Lihir Island

    Jan 1, 2011

  • SME
    Design of the Otjikoto Gold Mill, Namibia

    By John Rajala

    The Otjikoto Gold Mill was commissioned during November–December 2014 as Namibia’s first new gold producer in 30 years. Its operations consist of surface mining with a modern gravity/carbon-in-pulp mi

  • SME
    Design of the Otjikoto Gold Mill, Namibia "Mining, Metallurgy & Exploration (2021)"

    By John Rajala

    The Otjikoto Gold Mine in the Republic of Namibia is located approximately 300 kilometers north of the capital city of Windhoek. The project features surface mining with a modern gravity/carbon-in-pul

    Oct 30, 2020

  • CIM
    Design of the Pierina Waste Dump

    By P. Mark. Hawley

    Development of Barrick Gold?s Pierina Gold Mine in north-central Peru requires construction of a waste dump for disposal of non-ore grade materials stripped from the open pit to expose the ore. The wa

    May 1, 2002

  • CIM
    Design of the Pierina waste dump

    By R. Sharon, P. M. Hawley, X. Ochoa

    "Development of Barrick Gold’s Pierina gold mine in north-central Peru requires construction of a waste dump for disposal of nonore grade materials stripped from the open pit to expose the ore. The wa

    Jan 1, 2003

  • AIME
    Design of the Primary Crushing Plant

    By L. R. MacLead

    Delivery of tailing to any part of the area by gravity from the ridge was found practicable. Experiments with asbestos-cement pipe proved it possible to use level pipe across the dams if it is fed thr

    Jan 1, 1942