TARP — The Des Plaines Tunnel System (North Leg) A Case History
By Robert Rautenberg, Paul McDermott
This paper will discuss the construction of 15.9 km (9.88 mi) of tunnels on a project in Chicago, Illinois. The tunnels were driven utilizing two rock and four soft ground TBMs ranging in sizes from 7
Jan 1, 1997
-
TARP—Torrence Avenue Tunnel
By Bob Rautenberg, Luminita Calin
The Tunnel and Reservoir Plan (TARP), commonly known as the Deep Tunnel Project, was developed by the Metropolitan Water Reclamation District of Greater Chicago as a two-phase solution to the problem
Jan 1, 2001
-
Taxation Considerations in Mining/Exploration
The cost of constantly extending a decline tunnel that plays a part in the actual extractive process is a revenue cost. The characteristics of such a decline tunnel are that it is dug in a series of
Jan 1, 1990
-
Tbe Musconetcong Tunnel
By Henry S. Drinker
THE Musconetcong tunnel is situated in New Jersey, near the line of the Central Railroad of New Jersey, about twelve miles from Easton, on the Easton and Amboy Railroad, the latter being the extension
Jan 1, 1875
-
TBM and Logistics for Constructing Twin Tunnels Between Artificial Islands in Hampton Roads - RETC2021
By Sergio Estebanez, Martha Gross, Ruben Rubal, Yvonnick Rescamps, Alexandre Cochennec
The Hampton Roads Bridge-Tunnel (HRBT) Expansion project in coastal Virginia, USA will add two 1.5-mile (2.4 km) TBM bored tunnels alongside two existing immersed-tube tunnels between artificial islan
Jun 13, 2021
-
TBM And NATM Combined Solution For A Very Deep Tunnel?The ?Pajares? Case
By Enrique Fernández
INTRODUCTION The high speed rail link between Madrid and Asturias, in the North of Spain, has encountered in the Cantabrian range the biggest challenge of the whole line, a very deep tunnel, 25 km l
-
TBM Breakthrough in Pressurized Conditions—Ship Canal Water Quality Project (SCWQP) - NAT2024
By Francesco Chiappalone, Marco Invernizzi, Franco Gasperin, Fabrizio Fara
As part of the Ship Canal Water Quality Project, 2.7-mile Combined Sewer Overflow tunnel is excavated with a 21.5-foot diameter EPB Tunnel Boring Machine. Due to the difficult geological and hydrogeol
Jun 23, 2024
-
TBM Breakthroughs in Pressurized Conditions—Three Rivers Protection and Overflow Reduction Tunnel (3RPORT) and Northeast Boundary Tunnel (NEBT) Projects - NAT2022
By Francesco Chiappalone, Filippo Azzarà, Raffaele Aliberti, Daniele Nebbia, Lance Waddell
As part of the 3RPORT and NEBT Projects, 5-mile Combined Sewer Overflow Tunnels were excavated with a 19 ft diameter Slurry and 26 ft diameter EPB Tunnel Boring Machines. Due to the difficult geologic
Dec 1, 2022
-
TBM cutting forces with particular reference to cutter and tunnel diameters
By S. Okubo, K. Fukui
Empirical equations established for estimating the rock strength of the working face based on the cutting forces of a tunnel boring machines (TBM) are further examined and discussed with respect to th
Jan 1, 2003
-
TBM Data and Performance Monitoring on Large Diameter TBM Tunnels Lined with Shotcrete in the Himalayas—A Case Study - RETC2021
By Gary Peach, Peter Mason
Planning and estimating progress rates and costs for tunnelling is always best done based on experience and historic precedent. Much precedent is available but the use of data monitoring, data mining
Jun 13, 2021
-
TBM Data Management And Quality Assurance For The Brightwater Conveyance Project
By Jeffrey Mitsopoulos
King County?s (KC) Brightwater Conveyance Project in Seattle, Washington involves the construction of approximately 21 kilometers (13 miles) of bored tunnel, in three contracts, with four TBM?s which
-
TBM Design and Performance of Today - A Rapid Development - Where Will it End?
The last decade has seen a very rapid development in TBM tunnelling. Some trends are purely technical or economical and others relate more to preferences of different interests. Power levels have more
Jan 1, 1993
-
TBM Excavability: Prediction and Machine–Rock Interaction
By Z. T. Bieniawski, José Miguel Galera, Benjamín Celada
TBM case histories from over 400 tunnel sections are analyzed presenting a comprehensive application of the Rock Mass Excavability (RME) index (Bieniawski et al.2006). The paper introduces two new adj
Jan 1, 2007
-
TBM Excavation Of Rogers Pass Railroad Tunnel
By Gail B. Knight
INTRODUCTION In May 1984, The Canadian Pacific Railway awarded to the Joint Venture of Foundation of Canada, Ltd. of Toronto, Atlas Construction Co. of Montreal, and S. A. Healy Co. of Chicago the
Jan 1, 1987
-
TBM Excavation Through Pre-Existing Tie-Backs—Ship Canal Water Quality Project (SCWQP) - NAT2024
By Francesco Chiappalone, Franco Gasperin, Fabrizio Fara
This document describes the challenging task of mining through tiebacks using a 21'-8" diameter Tunnel Boring Machine (TBM) as part of the Ship Canal Water Quality Project. The mining operation involv
Jun 23, 2024
-
TBM Operation Challenges at DTL3 C931 Project in Singapore
By Bo Kyung Sim, Dae Young Kim, Jae Won Lee, Ebrahim Farrokh
"The contract C931 of the downtown line 3 (DTL3) mass rapid transit system of Singapore includes half a kilometer twin tunnels running between Mattar and Macpherson stations. An EPB TBM of 6.6 m diame
Jan 1, 2016
-
TBM Performance At Four Hard Rock Tunnels In California
By Tim Avery, Steve Klein, Mark Schmoll
Tunnel boring machine (TBM) performance in hard rock is highly dependent on the geologic conditions, including the type of rock and hysical properties like the rock strength, hardness, and the spacin
Jan 1, 1995
-
TBM Recovery Shaft Construction - SR-99 Tunnel
By Lance Rasband, Richard Hanke, John Starcevich
"The 17.4 meter (57 ft) diameter tunnel boring machine (TBM), the world’s largest at the time of her launch in 2012, locally referred to as “Bertha,” is stuck. Incapacitated due to mechanical failure
Jan 1, 2016
-
TBM Removal Within the Busiest Passenger Interlocking in the United States - RETC2021
By Devan Naik, Matthew Stokes, Andy Nigro
This paper describes the surgical removal of a 24 ft dia. Slurry Shield TBM entombed beneath one of the country’s busiest commuter rail interlockings, the Harold Interlocking in Queens, NY, and the co
Jun 13, 2021
-
TBM Rescue Shaft, Tunnel, and Relaunch in Karst Conditions - NAT2024
By Dan Swidrak, Bill Zietlow
Halfway through a 17,770-ft long stormwater tunnel, an 11-ft diameter TBM encountered a karst void below the Mississippi River in Missouri, resulting in significant inflow. It was decided that the TB
Jun 23, 2024