    The Alptransit Lötschberg Project, Switzerland: High Performance Wet-Mix Sprayed Concrete During TBM Excavation of Two High-Speed Railway Tunnels

    By Jens Classen, Thomas Kurth, Karl G. Holter

    High performance sprayed concrete equipment installed on two 9.4 m diameter hard rock TBMs enabled a continuous sprayed concrete lining for the entire contour in both tunnels to be performed concurren

    Jan 1, 2003

  • SME
    The Pannerdensch Kanaal Tunnel, Unique in Its Kind

    By F. Dudouit, M. M. Mohkam, F. Renault

    The Pannerdensch Kanaal Tunnel is part of Holland’s Betuweroute high speed freight railway project linking Rotterdam to inland of Europe. It comprises of twin tunnels, 1620 m long each, with 8.6 m inn

    Jan 1, 2003

  • SME
    Design-Build: Elevating Partnering to a Higher Level

    By Curtis A. Pledger, H. Lee Wimmer, I. Michael Gowring

    The Upper Diamond Fork Project, as part of the Central Utah Project Completion Act, conveys water six miles from the existing Sixth Water Aqueduct to the Diamond Fork Pipeline. During design, a Value

    Jan 1, 2003

  • SAIMM
    Tailings based pipe-support systems

    By C. E. Hales

    In an effort to improve efficiencies and reduce costs, AngloGold has embarked on a process to develop and deliver consistent, high quality, tailings based support or construction products to stopes an

    Jan 1, 2003

  • DFI
    Jacked Tunnel Construction

    "Boston’s Central Artery passes beneath nine active railroad tracks carrying commuter and Amtrak trains into South Station, the City's busiest rail terminal. These railroad operations had to remain in

    Jan 1, 2003

  • SME
    South Interceptor Tunnel Construction Using a Lovat EPBM

    By Dennis Molvik, Omar Fulton, Chris D. Breeds, Don Gonzales

    This paper presents and describes the South Interceptor Parallel Phase III Contract C93012C, which involved construction of a nominal 2.7 m (9-ft) finished diameter sewer conveyance using both pipe ja

    Jan 1, 2003

  • SME
    Board of Consultants–A Requirement for Hard Rock Tunneling Projects

    By Debbie Nakamura, Daniel Tempelis, John E. Shamma

    The Metropolitan Water District of Southern California established a Board of Consultants to assist them in administering the design and construction of the Inland Feeder Program tunnels. The Board ac

    Jan 1, 2003

  • SME
    The True Cost of Boulders in a Soft Ground Tunnel

    By Hugh E. Cronin, Joseph J. Coluccio

    The Columbia Slough Consolidation Conduit Project is a 12 ft. 0 in. inside diameter—15 ft. 4 in. excavated diameter tunnel, 8,300 lf. in length. The tunnel is divided in two parts a 4,460 lf. reach to

    Jan 1, 2003

  • SME
    Analysis of the Controlled Deformation in Rock and Soil (A.DE.CO.-RS)–Tunneling Approach Performance of an Alternate Tunneling Approach in the Construction of 100 Kilometers of Tunnel for the Bologna to Florence High Speed Rail Line

    By Silvano Morelli, Giovanna Cassani, Renzo Bindi, Antonio Nicola

    More than 70 km of main line and service tunnels have been excavated to date for crossing the Apennines between Bologna and Florence. A new design and construction approach, known as Analysis of t

    Jan 1, 2003

  • SAIMM
    Design and construction of tunnel portals under difficult geotechnical conditions

    By R. M. Spang

    Abstract Between the German city of Dresden and the Czech capital Prague a 4-lane highway is under con-struction. At the outskirts of Dresden it will cross the narrow and deeply eroded Weißeritz V

    Jan 1, 2003

  • SME
    The Design and Manufacture of the Arrowhead Tunnels Project Precast Segmental Lining

    By Christopher Hebert, Michael R. King, Mehdi Ghazi

    The Inland Feeder project is a critical component of Southern California’s water delivery system, relying on a strategic plan of water transfer and storage to enable the delivery of an additional 650

    Jan 1, 2003

  • SME
    Transportation Tunnel Rehabilitation

    By Paul M. Godlewski, Roberto J. Guardia

    Hundreds of highway and rail transportation tunnels in North America have been rehabilitated in the last two decades. Tunnel rehabilitation is usually dictated by an owner’s need to extend the working

    Jan 1, 2003

  • SAIMM
    Effect of the strain rate and water stauration for the tensiles strength of rocks

    By I. Matsunaga, K. Aoki, W. -j. Jung

    Blasting is widely used in mining and basic construction because of its speed and economy to destroy the rocks. Blasting has the advantages of reduced excavation costs and shorted construction time wh

    Jan 1, 2003

  • SME
    South Mountain Water Facilities–Reach 3B

    By Mark R. Rybak, James Delmonte, Travis Hartman

    The City of Phoenix, Arizona designed a 7.2 km (4.5 mi) long water transmission main from the South Mountain Reservoir to the Ahwatukee Foothills Reservoir to address the growing demand for drinking w

    Jan 1, 2003

  • CIM
    CERM3 and its contribution to providing sustainable research for the mining industry

    By M. Veiga, L. Lavkulich, R. Pakalnis, M. Ghomshei, S. Baldwin, J. A. Meech

    "On July 26, 2000, the Canada Foundation for Innovation announced an award of $1.3 M dollars for The Centre for Environmental Research in Minerals, Metals and Materials, CERM3, at The University of Br

    Jan 1, 2003

  • SME
    Flexibility of NATM Shown During the Construction of the Egge Tunnel/Germany

    By Josef Arnold, Norbert Fuegenschuh

    The “Eggequerung” is an important part of the German Railway’s (Deutsche BahnAG) modernized Dortmund—Kassel line. The heart of this 13-km-long (8 miles)construction lot is the double-track Egge Tunnel

    Jan 1, 2003

  • SME
    Shotcrete Lining Design: Factors of Influence

    By Bruno Mattle, Max John

    For tunnels with low overburden, the shotcrete lining is the main element of ground support, which is why shotcrete behavior is of prime importance. Following its application, shotcrete not only gains

    Jan 1, 2003

  • SME
    Is Design Build for Chicago Area Tunnel in the Cards?–Cady Marsh Drainage Ditch and Tunnel/Pipeline Project, Griffith, Indiana

    By Faruk Oksuz, Clay Haynes, David Egger

    The United States Army Corps of Engineers (USACE) has committed to solve a major drainage problem in the suburban Chicago community of Griffith, Indiana. The Cady Marsh Ditch is currently undersized a

    Jan 1, 2003

  • SME
    Dublin Port Tunnel–Construction of One of Europe’s Biggest Urban Road Tunnels

    By Martin Knights, Geoff Featherstone, John Flanagan, David Lawrence

    The proposed paper will address specific transport, engineering, environmental and community related issues concerning the current construction and future operation of Europe’s biggest urban road tunn

    Jan 1, 2003

  • SME
    Tunnelling for the Channel Tunnel Rail Link

    By David Court, Rab Brown

    The paper discusses the work in progress on the construction of the extension of the High Speed Rail line from the Channel Tunnel into the centre of London UK known as the “Channel Tunnel Rail Link” (

    Jan 1, 2003