    Slope Steepening Investigations for the Valley Pit at the Teck Highland Valley Copper Mine Using Presplit Blasting

    By Nick Rose, Mathieu Veillette, Matthew King

    "The Teck Highland Valley copper (THVC) mine is located approximately 55 km (34 miles) southwest of Kamloops and approximately 20 km (12 miles) west of Logan Lake, BC, Canada (Fig. 1). Mining at THVC

    Apr 1, 2019

  • SAIMM
    Geotechnical Data Analysis to Select a Feasible Method for Development of a Long Axis, Large Diameter Vertical Ventilation Shaft

    By E. J. Walls, W. C. Joughin

    "In selecting a suitable method to sink a vertical shaft for underground access, a number of constraints influence the ultimate decision of where and how to develop the shaft, not least among these be

    Apr 1, 2019

  • SME
    Managing Tailings Influenced Ground Water at the Butte Superfund Site

    By R. D. Williams

    "In a very real sense, Butte, MT is where the copper came from that won two world wars. The price for that unrestricted mining and smelting of copper came due in 1983 when Butte was declared a Superfu

    Apr 1, 2019

  • SAIMM
    Limiting the Influence of Extreme Grades in Ordinary Kriged Estimates

    "The management of outlier grades in positively skewed gold distributions is a contentious issue. Incorporating outliers in standard ordinary kriging (OK) estimation procedures in a way that honours t

    Apr 1, 2019

  • SAIMM
    South Africa’s Options for Mine-Impacted Water re-use: A Review

    By T. Grewar

    "South Africa is a water-scarce country, rated as one of the 30 driest countries in the world. Worryingly, government expects water demand to outstrip supply as early as 2025. The South African govern

    Mar 1, 2019

  • SAIMM
    Key Aspects of Bench Flotation as a Geometallurgical Characterization Tool

    By V. Ross

    "Bench-scale flotation tests play a major role in the geometallurgical process value chain. Despite their apparent simplicity, these tests pose pitfalls in terms of operation, as well as the interpret

    Mar 1, 2019

  • SAIMM
    A Spatial Mine-to-Plan Compliance Approach to Improve Alignment of Shortand Long-Term Mine Planning at Open Pit Mines

    By T. J. Otto, C. Musingwini

    "The objective of any mining company is to sustainably maximize the net present value (NPV) throughout the life-of-mine (LOM). The expected NPV over the LOM is calculated based on a mine plan, yet the

    Mar 1, 2019

  • SAIMM
    Financing Diamond Projects

    "Investment in diamond exploration has been declining over the past decade, in spite of positive long-term industry fundamentals and a growing interest in diamonds as an investment category. The lack

    Feb 1, 2019

  • SAIMM
    Recycling Pre-Oxidized Chromite Fines in the Oxidative Sintered Pellet Production Process

    By D. Paktunc, S. P. du Preez, J. P. Beukes, P. G. van Zyl, A. Jordaan

    "The chromium (Cr) content of stainless steel originates from recycled scrap and/or ferrochrome (FeCr), which is produced mainly by the carbothermic reduction of chromite ore. The oxidative sintered p

    Feb 1, 2019

  • SAIMM
    Monitoring the Performance of DMS circuits using RhoVol Technology

    By T. Steyn, M. Fofana

    "One of the most important performance indicators of a dense medium cyclone (DMC) circuit is the Tromp curve, and by extension the separation density and Ecart Probable (Ep) values. The densimetric pr

    Feb 1, 2019

  • SAIMM
    A Strategy for Improving Water Recovery in Kimberlitic Diamond Mines

    By A. J. Vietti

    "Drought conditions and the possible lack of sufficient raw water supply are a constant reminder to the Southern African diamond miner of the need to minimize raw (new) water input while maintaining o

    Feb 1, 2019

  • SAIMM
    Operational Changes Enable Namdeb’s Southern Coastal Mining Team to Reduce Risk and Increase Productivity as We Advance Deeper into the Atlantic Ocean

    By S. Kirkpatrick, J. Mukendwa

    "The mining operation at Namdeb’s Southern Coastal Mine (SCM) is unique. It targets gravel layers up to 30 m below sea level, which continue to dip deeper, further west, under the Atlantic Ocean. On t

    Feb 1, 2019

  • CIM
    Mako Single Stage Sag Mill Comminution Circuit Design, Commissioning and Ramp-Up

    By P. Scinto, P. Hudson

    "Modern day ore bodies are becoming increasingly harder, more abrasive and lower grade. The Mako deposit is located in Senegal and consists predominantly of primary mafic and felsic lithology that are

    Jan 1, 2019

  • CIM
    The Simulation and Analysis on Die Casting Process of Copper Rotors

    By Mi, Dong Liang, Jingyuan Bai, Victor Zhou, Xujun

    Squirrel cage induction motors are the mostly used motors at present. Currently, the rotors of the squirrel cage induction motors are produced by aluminum die casting technique with the advantages of

    Jan 1, 2019

  • CIM
    The First Electrolytic Copper Refinery in the USA at the Chemical Copper Co. Phoenixville, Pa – History Revisited

    By E. Wraith, W. W. Culver, B. Wesstrom, P. J. Mackey

    Electrodeposited copper of the 1860s was of unprecedented purity, although the profound significance of this achievement was not fully realised until the dawn of the electrical age a decade or so late

    Jan 1, 2019

  • CIM
    Implementation of APC at Freeport-Mcmoran’s (FMI) Morenci Metcalf Concentrator

    By A. Supomo, H. Resendiz, C. Burbidge

    "Freeport-McMoRan Inc. (FMI) commissioned the expansion of the Morenci Metcalf concentrator in 2014. The concentrator included many design and equipment innovations, including the first-of-its-kind Me

    Jan 1, 2019

  • CIM
    The Development of Pan American Silver’s La Colorada Shaft

    By Martin G. Wafforn, George J. Greer

    "In early 2014, Pan American Silver Corp. commenced a project to construct a second shaft at its La Colorada underground mine located in Zacatecas State in Mexico. This was the first new shaft develop

    Jan 1, 2019

  • CIM
    Shaft Sinking in the Next Five Decades / 2070

    By William M. (Bill) Shaver

    "The author will review the early history of shaft sinking as well as focus on the improvements made in shaft design and construction over the last fifty years (1970 to 2019) to predict how shaft sink

    Jan 1, 2019

  • ISEE
    Delineating Extent of Cracks in Post-Blast Rock Surface Using GPR – A Case Study

    By Sayantan Chakraborty, Kaushik Dey, SaKaushik Dey tyabrata Behera

    Drilling and blasting is a popular excavation technique in the drift of underground mine. Faster completion of drift reduces the gestation period and thus longer blast pulls are attempted with longer

    Jan 1, 2019

  • SME
    Interpreting Backfill QA/QC Test Data: Do We Need an Industry Standard?

    By D. Stone, R. Pakalnis, B. Seymour

    Most mines using backfill routinely carry out quality control (QC) testing of backfill mixes with unconfined compression test cylinders. This is true for paste operations, hydraulic fill operations, a

    Jan 1, 2019