Installation of No 2 Gold Plant - Shotover River
L&M have been involved on the Shotover since 1980 when we joined Jack and Barney Ryan, who had started in 1972 with gold at $45 per ounce after a successful career as roading and demolition contra
Jan 1, 1985
-
Underground Mining Construction by Contract - Getting the Best for Principal and Contractor
Contractors are used extensively in the development of underground mines in Australia. Often problems arise, some originating as far back as the feasibility stage of projects, through inexperience, la
Jan 1, 1985
-
Tools for the Development of Metallurgical Processes
By Gray N. B
The need to improve existing metallurgical processes and to develop new processes to meet the economic challenges that lie ahead requires the application of the tools of process analysis viz. mathemat
Jan 1, 1985
-
Mining Methods at Agnew Nickel Mine, Western Australia
By Myers PA, Noble MR, Lawrence JS, Cannings WR
The Perseverance orebody presents the Agnew Mine with a wide variety of geological settings, necessitating the application of several mining methods within the limited strike length being extracted.Mi
Jan 1, 1985
-
Primary vertical Crafter Retreat Mining at the Zinc Corporation, Limited
By Hebbard GJ
Vertical crater retreat mining is being used at Zinc Corporation, Limited and New Broken Hill Consolidated, Limited for pillar recovery between previously mined and filled stopes. In order to increase
Jan 1, 1985
-
Computer Assisted Remote Control and Automation System for Longwall Shearers
By De Janti VP
The automation and centralized monitoring of longwall type underground mining is presently an important subject matter of research in France. The purposes are :to improve safety and working conditions
Jan 1, 1985
-
Technological Innovations to Reduce Operating Cost at Kalgoorlie Nickel Smelter
By Remilton D, Raston GR
The low price of nickel which has prevailed since 1982 has dictated that unit production costs must be minimised. Early in the crisis, a decision was made within Western Mining Corporation to reduce u
Jan 1, 1985
-
The Development of Hunter Valley Coal Preparation Plant
By White PJ, Worrad C
The Hunter Valley Coal Preparation Plant and associated materials handling facilities commenced operation in mid 1982. The new plant and coal handling system were designed to integrate with existing m
Jan 1, 1985
-
Failure Rate of Process Computers
By Weber W
Methods of calculation of the reliability of process computers are getting more and more important. The paper presents long period observations of 21 process computers with online applications in the
Jan 1, 1985
-
Corrosion and Fouling Control in a Cooling Water System
By Tobin GJ
Testwork carried out in the cooling water circuit at the Yabulu treatment plant of the Greenvale Joint Venturers (Metals Exploration Queensland Pty. Ltd. and Freeport Queensland Nickel Incorporated) s
Jan 1, 1985
-
Commodity - Linked Borrowing Opportunities for Resource - Oriented Projects and Companies
The traditional form of project financing for resource related projects has involved project financings structured with either recourse to the project sponsor(s) or commercial banks accepting the proj
Jan 1, 1985
-
Fluxing Requirements for Copper Smelting Slag
Silica and limestone fluxing levels in copper smelting slags were studied. Copper concentrates with flux additions were smelted to matte (55.5 per cent Cu) and slag in a pilot scale submerged combusti
Jan 1, 1985
-
Gas Properties of Australian Coal
By Hargraves A. J
At 4 MPa gas pres ure and 30°C the sorptive capacity of 10 selected Australian dried coal ranges from 17 to 23 m3/tonne of CH4 and 27 to 36 m3/tonne of CO2. Values for moist coals are about 25 pe
Jan 1, 1985
-
Bringing the Croesus Shaft Back into Production
By Warren R
Croesus Shaft is one of two operating shafts on North Kalgurli Mines Limited's Fimiston lease.At the cessation of gold mining in 1974, the workings at Croesus were allowed to flood. Large quantit
Jan 1, 1985
-
Monitoring and Control in the Recirculation of Underground Ventilation Air
By Walker K, Burton RC
An outline of the ventilation and refrigeration requirements of deep South African gold mines is presented. This is followed by a brief description of the history of controlled recirculation in mines
Jan 1, 1985
-
On Bounding Techniques for the Optimum Pit Limit Problem
By Giannini L. M
The determination of the "optimum pit limit" of a mine has long been considered as a fundamental problem of mine planning. A number of mathematical techniques have been proposed to solve thi
Jan 1, 1985
-
The Potential for Automation and Process Control in Coal Preparation
Several coal preparation plants are presently "automated" to the extent of automatic sequencing and interlocking via digital means, together with closed loop control on various level and density circu
Jan 1, 1985
-
Gravity Cleaning of Fine Coal
Traditionally, the gravity cleaning of coal has been evaluated in pilot plant tests. Attention is now turning to the development of empirical models of gravity cleaning equipment that can be used for
Jan 1, 1985
-
Nineteenth Annual Report - 1984/1985
The past year has been a difficult one for the mining industry in this country, but an active and successful one for the Branch. Membership has continued to increase, albeit at a slower rate than last
Jan 1, 1985
-
Trends in Control System Equipment and Associated Data Networks
With the continuing move towards digital signal based control and measurement, it is inevitable that such technology will be increasingly employed on remote sites. The benefits of increased metallurgi
Jan 1, 1985