    Performance-Based Reliability Design for Deep Foundations Using Monte Carlo Statistical Methods (aa702b6b-e181-4fa5-97b3-2e3a1ab7040e)

    By Haijian Fan

    Currently, deep foundation designs for the service limit state are deterministic in nature. The settlements and lateral deflections of deep foundations are calculated by means of numerical techniques

    Jan 1, 2017

  • DFI
    Peribonka Dam In Canada A Showcase Of Advanced Ground Engineering Techniques

    By Mazin Adnan

    The 80m high dam at the Peribonka river in the Canadian province of Quebec was designed for the generation of 385 MW of hydro electrical power (Fig.1). The complex ground conditions required the e

    Jan 1, 2008

  • DFI
    Permanent Canal Closures and Pumps Cofferdams – Support of Deep Excavation in Soft Ground Using the Open Cell Sheet Pile System

    By Ryan Higbie, King Chin, Matthew Anderson, Mike Huggins, Rian Johnson, Dave Sinsheimer

    "The Permanent Canal Closures and Pumps (PCCP) project is the capstone piece of New Orleans’ extensive hurricane risk-reduction system constructed following Hurricane Katrina. The project consists of

    Jan 1, 2017

  • DFI
    Permanent Displacement And Pile Driving Vibrations - Summary

    By Charles H. Dowding

    Whenever piling vibrations are significant, construction activities associated with pile driving and/or excavation can produce permanent displacement. These permanent displacements are more detrimenta

    Jan 1, 1991

  • DFI
    Permanent Earth Retention for Deep Excavation Installed Within Minimal Right of Way Limits

    By Thomas D. Humbert, Christopher J. Ramsey

    Construction of a new underground parking structure in State College, Pennsylvania, is situated on a site constrained by limited ROW and required excavations ranging in depth from 25 ft to 40 ft. Addi

    Jan 1, 2019

  • DFI
    Permanent Soil Nail Earth Retention System, Stanley Hall Replacement Project, UC Berkeley

    By Pirooz Barar

    The new Stanley Hall building will house the center for bio-engineering and technology research for the UC Berkeley campus. The structure is located at the northeast part of campus, adjacent to Donne

    Jan 1, 2004

  • DFI
    Philadelphia Dock Story—Pile Challenges at Delaware River

    By Craig H. Olson

    "A new ship dock at a Philadelphia area refinery will be capable of docking the largest tanker to travel the Delaware River, the Stena V-MAX, which will induce significant lateral loads. The loads at

    Jan 1, 2008

  • DFI
    Philadelphia Dock Story—Pile Challenges at Delaware River (06bf9951-abf5-4656-aab7-81fa955662d4)

    By Craig H. Olson

    "Anew ship dock at a Philadelphia area refinery will be capable of docking the largest tanker to travel the Delaware River, the Stena V-MAX, which will induce significant lateral loads. The loads at t

    Jan 1, 2008

  • DFI
    Physical Modeling and Development of Design Criteria for Maintainable Drains for Earth Retention Systems

    By J. Erik Loehr, Andrew Z. Boeckmann

    "Poor drainage is a common cause of poor performance of earth retention systems, resulting in burdensome serviceability problems that can progress to outright failure of the retention system if not ad

    Jan 1, 2016

  • DFI
    Pier Design And Construction In Water Bearing Soils ? Synopsis

    By C. N. Baker

    The design and construction of drilled piers through water bearing and caving soil conditions are discussed. The need for close cooperation between the design engineer and contractor in both the desig

    Jan 1, 2010

  • DFI
    Pile Construction And Related Problems ? Synopsis

    By K. Fujita

    In order to deal properly with the fundamental aspects of pile construction, the following problems and their solutions are introduced: For driven piles - stresses, damage, movements of surroundings,

    Jan 1, 2010

  • DFI
    Pile Design According to Eurocode 7, Highlights and Developments

    By Adriaan van Seters

    "Abstract The content of Eurocode 7 – Part 1 and Part 2 – with respect to piled foundations is outlined. The important role of pile testing is presented and the derivation of the characteristic value

    Jan 1, 2014

  • DFI
    Pile Design And Construction Challenges In Partially Thawed Alaskan Soils

    By John D. Thornley

    Alaskan villages typically store a one-year supply of fuel to reduce significant delivery costs. Alaska Village Electric Cooperative (AVEC), an electric utility cooperative providing power to 51 Alas

  • DFI
    Pile Design and Construction Challenges in Partially Thawed Alaskan Soils (f9ca4371-20bf-4196-a495-4aa1bd15a8c0)

    By John D. Thornley

    Alaskan villages typically store a one-year supply of fuel to reduce significant delivery costs. Alaska Village Electric Cooperative (AVEC), an electric utility cooperative providing power to 51 Alask

    Jan 1, 2017

  • DFI
    Pile Design For Offshore Structures Subjected To Subsidence

    By Juan J. Campo

    The Freeport-McMoRan Main Pass Mine development in the Gulf of Mexico is a complex designed to extract up to 67 million long tons of sulphur over a 40 year period. The initial development includes 15

    Jan 1, 1992

  • DFI
    Pile Design Philosophies For Coralline And Weak Carbonate Rocks

    By Rahul Wankhade, Sunil S. Baswankar, Aditya S. Kharatkar

    Despite advances in pile design methodologies and piling techniques at site, difficulties and uncertainties still exists for design of piles particularly in coralline deposits and weak carbonate rocks

    Sep 1, 2022

  • DFI
    Pile Design Using Cpt Results: The “Lpc Method”

    By Frederic A. Verheyde

    The CPT pile design method of the ‘Laboratoire des Ponts et Chaussées’ (LPC) uses the cone resistance (qc) for the design of axially loaded piles. It was originally proposed in 1982 and was revised in

    Nov 1, 2022

  • DFI
    Pile Design, Testing, And Installation For A Gated Dam ? Synopsis

    By B. H. Moore

    The opportunity to evaluate the pile design procedures used on a major project is an infrequent occurrence. It is even more infrequent that the project involves piles with significant tension and hori

    Jan 1, 2010

  • DFI
    Pile Diameter Effects On Initial Modulus Of Subgrade Reaction For Laterally Loaded Piles

    By Hubert Law, Amin Rahmani

    This paper evaluates the effects of pile diameter on the initial modulus of subgrade reaction and proposes modifications to the subgrade reaction moduli that are commonly used in the current state of

  • DFI
    Pile Driving Between the Amazonas and Xingu Rivers in the Tucuruí-Manaus Transmission Line – Lessons Learned and Solutions Found for a Challenging Project

    By José Carlos do Amaral, Marcelo Groszownik, Jorge Beim

    "Initiated in 2008, the project of this 1800 km long Electrical Transmission Line is a job of extreme technical complexity, crossing regions of major forests and rivers. When ready, it will allow the