Evaluation of New Techniques For Thin-Seam Mining
By Jasinder S. Jaspal
The United States has very large coal reserves in seams that are less than 1065 mm (42 in.) thick. These reserves are often not mined because of the difficulty of working in low heights and, in most c
Jan 1, 1992
-
Use of a Rule-based Strategy to Control a 7-Foot Cone Crusher
By W. J. Whiten
A rule-based control system was developed for a 7-foot Hydrocone crusher with automatic set regulation, based on operating data collected in the field. When implemented in a plant PLC, the system was
Jan 1, 1992
-
Olivine, The Industrial Mineral
By Jr. Smith
Industrial minerals are just other rocks, except for the unique characteristics that make them useful in an industrial process. There is not a ready market for this type mineral and one or more uses m
Jan 1, 1992
-
Real-Time pH Control Using Fuzzy Logic And Genetic Algorithms
By C. L. Karr
Establishing suitable control of pH, a requirement in a number of mineral and chemical industries, poses a difficult problem because of inherent nonlinearities and frequently changing process dynamics
Jan 1, 1992
-
Real Time Grade Control In Mine-Planning & Production ? Introduction
By Simon W. Houlding
This paper summarizes recent developments in computer modelling and estimation technology. Significant improvements in computational and modelling efficiencies have advanced technical computing to the
Jan 1, 1992
-
Environmental Impact of Gold Ore Processing
By H. M. Conger
I'm really very pleased to be talking with you today about the environmental impacts of gold ore processing as part of this symposium on emerging process technologies for a cleaner environment.
Jan 1, 1992
-
New Cone Crusher Designs
By Jerry Motz, Gary Beerkircher
Through a joint development program between Bougainville Copper Ltd. and Nordberg, the MP1000 cone crusher was developed and tested during the period between 1982 and 1987. Following the successful pr
Jan 1, 1992
-
Environmental And Economic Risk Assessment/Management In Mine Development
By W. J. Roberds
A formal and explicit yet cost-effective approach is proposed to ensure that decisions made during mine development are optimum (with respect to their ultimate consequences) as well as defensible. Thi
Jan 1, 1992
-
Reserve Calculations: An Adventure In Geo-Fantasy?
By N. B. Prenn
Many recent projects have been developed and mined based upon imaginary reserves. Imaginary or "geo-fantasy" reserves have cost many companies millions of dollars. The significant and varied technolog
Jan 1, 1992
-
Equilibrium Capillary Pressure Measurements In Particulate Systems
By D. Diggins
Experimental apparatus for the determination of powder wettability is described. The principle of the technique is based on the measurement of the equilibrium capillary pressure in a packed bed of par
Jan 1, 1992
-
Computer Based Input-Output Modelling For Autogenous Mill Control
By Roy Eric Lurie
Computer based signal processing techniques for obtaining empirical dynamic models from measured mill circuit data are discussed. This modelling is the first step towards designing a particle size con
Jan 1, 1992
-
Optimum Mine Designs to Minimize Coal Blimps: A Review of Past and Present U.S. Practices
By Matthew J. DeMarco, Anthony T. Iannacchione
Coal bumps have presented serious mining problems in the U.S. throughout the 20th Century. Fatalities and injuries have resulted when these destructive events occur at the working face. Persistent bum
Jan 1, 1992
-
Applications of Risk Assessment Techniques in RCRA Clean Closure of Surface Impoundments With Trace Metal Contamination
By R. Kadeg, S. Pavlou
A methodology for developing and utilizing risk-based action levels for soils in site closures is discussed. The methodology is based on standard exposure pathway models which are consistent with curr
Jan 1, 1992
-
Decision of Mount Isa Mines Limited to Change to Autogenous Grinding
By V. P. Keran, K. Leung
Two 32 foot x 14% foot, 6.4 MW autogenous mills have been installed in the Mount Isa Mines Copper Concentrator to replace the fine crushing plant, fine ore bin, rod mills and primary ball mills. This
Jan 1, 1992
-
Discussion – Engineering to Reduce the Cost of Roof Support in a Coal Mine …- Mining Engineering, Vol. 43, No. 8 pp.1062-1065 – Khair, A. W. and Peng, S. S.
By S. Serata
Background Results of the above study in the August 1991 issue of Mining Engineering offer valuable lessons in the solution of cutter-roof problems. The original study plan was initiated by the dis
Jan 1, 1992
-
Control of Diesel Particulate Emissions in Underground Coal Mines
By Robert S. Ondrey, Robert A. Haney, David J. Atchison
The Mine Safety and Health Administration has conducted tests to determine the effectiveness of two methods for reducing diesel particulate emissions in underground coal mines. Both methods involved c
Jan 1, 1992
-
Pebble Crushing Test In A Sag Mill Circuit
By D. E. Healy
In 1989 an Autogenous Grinding Task Force was formed to study potential autogenous grinding circuits to replace the existing semi-autogenous grinding at the National Steel Pellet Plant located in Keew
Jan 1, 1992
-
Borehole Mining: Improved Technology Expands Horizon
By M. F. Dibble
Borehole mining, as a viable concept for recovering deep sedimentary mineral resources, historically has been long on promise but short on results. Application of the technology seems best suited for
Jan 1, 1992
-
Economic Potential Of Malanjkhand Proterozoic Porphyry Copper Deposit, M. P. India
By D. B. Sikka
Porphyry type copper ± molybdenum deposits typically occur in the Phanerozoic rocks and have been well documented. During the past two decades a number of porphyry type Cu ± Mo deposits which range in
Jan 1, 1992
-
Sensitivity Analysis Of 3-D Model Block Dimensions In The Economic Open Pit Limit Design
By Wen L. Cai
This paper examines the effects of different block dimensions and cone bases on the economic open pit limit design based on case studies on a coal deposit consisted of two west- east elongated, near v
Jan 1, 1992