  • SME
    Shock Reduction For Low-Coal Shuttle Car Operators Using Viscoelastic Seating Foam (28c35e03-ef42-4f21-bba8-a2b145516a70)

    By A. Mayton

    The prolonged exposure of equipment operators to shock and whole-body vibration (WBY) is linked to cumulative back, neck, and abdominal disorders. In low-coal mines, space restrictions make seat suspe

    Jan 1, 1998

  • SME
    Short Course - Surface and Underground Mine Modeling With Computers

    By Betty L. Gibbs

    A short course, held during the SME Annual Meeting in Phoenix, AZ in February, focused on software for surface and underground mine modeling. The objectives of the short course were to review techniqu

    Jan 1, 1992

  • SME
    Short Cycle Back-Pulse Filtration And Computer Modeling Of Ccd Circuits By Iterative Solver

    By Gordon R. S. Smith

    This paper is in two parts. The first part describes Membrane Back-Pulse Filtration and the effects of very short filter downtimes on cycle filtration rates. Part II describes the use of Membrane Ba

    Jan 1, 1991

  • SME
    Short History Of Man And Gold

    By Thomas V. Mullen

    Some 146 kt (4.69 billion oz) of gold have been mined throughout history. Of this, 70% has been mined in this century alone, with 17% produced from 1985 through 1996 (Fig. 1 and Table 1). Until the m

    Jan 1, 1998

  • SME
    Short Mountain Silica – A New Producer in Tennessee

    By Mark J. Zdunczyk

    Short Mountain Silica mines the Clinch Formation, an orthoquartzite, for silica sand. The operation is located near Mooresburg, TN, about 80 km (50 miles) northeast of Knoxville. Short Mountain is

    Jan 1, 1992

  • SME
    Short Mountain Silica: A New Venture In Silica Sand Production

    By M. J. Zdunczyk

    Located approximately 50 miles northeast of Knoxville, Tennessee, Short Mountain Silica mines the Clinch Formation, an orthoquarzite, for silica sand. In 1980, a Knoxville resident and area contractor

    Jan 1, 1992

  • SME
    Short scale spatial variability of sulfur in a coal seam

    By R. W. Barbaro, R. V. Ramani, K. V. K. Prasad, P. T. Luckie

    The limitation of sulfur dioxide in power plant In this study, the following quality parameters of the coal emissions dictates that sulfur in coal be reduced to the lowest possible level before combus

    Jan 1, 1991

  • SME
    Short Startup for a High Pressure Mixshield Tunnel Boring Machine - RETC2021

    By Matthew Burdick, Andrew Rule, Erica Bailey

    The Second Narrows Water Supply Tunnel, Burrard Inlet Crossing project for the Greater Vancouver Water District entails deep shaft construction, subway sized pressurized face tunneling through highly

    Jun 13, 2021

  • SME
    Short term mine planning and grade control practice at the Mesquite mine

    By P. Brumit, L. Grady, R. Mitts, V. Holm

    The Mesquite mine is a large, open pit, heap leach gold mine owned and operated by Gold Fields Operating Co.-Mesquite. The mine uses a fully integrated mine planning and reserve modeling software syst

    Jan 1, 1991

  • SME
    Short Term Mine Planning And Grade Control Practice At The Mesquite Mine (b9fe8c31-659a-4850-a163-7cd7260c5540)

    The Mesquite mine is being operated by Gold Fields Operating Co.-Mesquite, a subsidiary of Gold Fields Mining Corp. The mine Is located in southeastern California about 56 km (35 miles) east of the fa

    Jan 1, 1989

  • SME
    Short Term Planning For Mining A Longwall Panel: An Application Of Geostatistics For Quality Control

    By R. W. Barbaro

    The limitation of sulfur dioxide in power plant emissions dictates that sulfur in coal be reduced to the lowest possible level before combustion so as not to aggravate the emission control problem at

    Jan 1, 1988

  • SME
    Short Term, Photoelastic, Roof Bolt Load Cell

    By Kenneth S. Graham, S. C. Gambrell

    A short term, simple roof bolt load cell which uses a birefringent (photoelastic) coating as its sensing element has been developed. The load cell is installed between the bearing plate and the nut/wa

    Jan 1, 1992

  • SME
    Short Tunnels = HIGH Risk?: Pipeline Construction Involving Open-Cut And Tunnel Segments

    By Michael Gilbert

    In the world of tunneling the glamour is in the large diameter, long tunnels, but perhaps the number of projects for small diameter and short length tunnels are greater and generally have higher risk

  • SME
    Short Tunnels with Shallow Cover

    By David Smith

    Construction of a new transportation link frequently requires crossing under an existing highway or railroad. Although traffic diversions may permit a cut and cover structure to be built, ‘zero impact

    Jan 1, 2005

  • SME
    Short-Delay Blasting At Anaconda's Berkeley Open-Pit Mine, Montana

    By Lewis L. Oriard

    The authors outline the development and application of blasting methods put into use 11 years ago at the Berkeley Open-Pit Mine, Butte, Montana. The blast design uses a very short delay (5 millisecond

    Jan 1, 1980

  • SME
    Short-Haul Opportunities For Moving Minerals By Rail ? Summary

    By B. M. Flohr

    Railroads are cost competitive with trucks for hauls greater than 500 miles - WRONG. Today I will tell you about many rail movements of less than 100 miles throughout the country. Rail is a short haul

    Jan 1, 1986

  • SME
    Short-Range Planning: From Scheduling to Sequencing

    By J. Schleifer

    On short term, planning techniques require more details to ensure feasibility, giving importance to operation constraints and use of available resources. In GUEMASSA (Morocco), the ore mass is min

    Jan 1, 1996

  • SME
    Short-Term Mine Production Scheduling For Industrial Minerals Using Multi-Objective Simulated Annealing

    By M. Kumral

    The in-situ mineral characteristics of a deposit are simulated by sequential co-simulation and averaging the simulated characteristics within specified block volumes creates a three-dimensional block

    Jan 1, 2002

  • SME
    Short-Term Planning In Sublevel Stoping Methods - Introduction

    By Fernando Muge

    A complex pyrite orebody located in the South of Portugal (MO INHO) was exploited in the past by cut and fill methods until a certain level. It was decided to design a new plant for non ferrous met

    Jan 1, 1979

  • SME
    SHORT-TERM PLANNING OF OPEN PIT MINES WITH SEMI-MOBILE IN-PIT CRUSHER - SME Annual Conference 2023

    By E. Ben-Awuah, H. Askari-Nasab, N. Al Habib

    Open pit mines are getting deeper with time and transportation expenses are increasing because of the increasing haulage distance. In-pit crushing and conveying (IPCC) is getting popular in deeper ope

    Feb 1, 2023